第1题:

157 Sensitivity analysis can be used in risk analysis to:

A. Substitute for uncertainty analysis in risk quantification

B. estimate the level of risk aversion adopted by management

C. estimate the effect of change of one project variable on the overall project

D. A and B

E. All of the above


正确答案:C

第2题:

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control


正确答案:B
定量风险分析过程分析风险事件的影响并对这些影响赋予一个数值化的评价。

第3题:

● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.

A.Risk Identification

B.Quantitative Risk Analysis

C.Qualitative Risk Analysis

.Risk Monitoring and Control


正确答案:B

第4题:

Which of the following is the best reason for the use of an automated risk analysis tool?下列哪个是使用自动化的风险分析工具最好的理由?()

  • A、Automated methodologies require minimal training and knowledge of risk analysis.自动化方法需要最小限度的风险分析知识培训
  • B、Most software tools have user interfaces that are easy to use大部分软件工具有易于使用的用户界面
  • C、Information gathering would be minimized and expedited due to the amount of information built into the tool.由于工具内置了大量的信息,信息收集过程将会缩减和加速
  • D、Much of the data gathere dduring the review cannot be reused for subsequent analysis.在评估期间大部分被收集的数据不能被重用为后续分析

正确答案:C

第5题:

( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality.

A.Quantitative Risk Analysis
B.Qualitative Risk Analysis
C.Enterprise Environmental Factors
D.Risk Management Plan

答案:B
解析:
翻译:(71)利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。A.定量风险分析 B.定性风险分析 C.企业环境因素 D.风险管理计划

第6题:

The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


正确答案:A
风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

第7题:

The ( ) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring anD.Control

答案:A
解析:
项目风险管理主要包括风险管理计划编制、风险识别、定性风险分析、定量风险分析、风险应对计划编制和风险监控。其中,风险识别过程是确定哪些风险可能会对项目产生影响,并将这些风险的特征形成文档。
A.风险识别 B.定量风险分析 C.定性风险分析 D.风险检测与控制

第8题:

Sensitivity analysis can be used in risk analysis to:

A Substitute for uncertainty analysis in risk quantification

B estimate the level of risk aversion adopted by management

C estimate the effect of change of one project variable on the overall project

D A and B

E All of the above.


正确答案:C