A network planning diagram shows a large internetwork with many routers. The configurations show that OSPF has been enabled on all interfaces, I P addresses correctly configured, and OSPF workinG. For which of the following cases would you expect a router to create and flood a Type 2 LSA?()
第1题:
● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between
them.
(73)
A.PERT
B.AOA
C.WBS
D.PDM
第2题:
is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the logical relationships that exist between them. A.PERT B.AOA C.WBS D.PDM
第3题:
The purpose of a dummy activity in an activity-on-arrow diagram is to:
A.Identify a task that could be replaced by another.
B.Take the slack time into account.
C.Show a task that is not necessarily needed.
D.Denote a milestone.
E.Show a dependency relationship.
第4题:
is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.
A.PERT
B.AOA
C.WBS
D.PDM
第5题:
A. the cause of routing errors.
B. the number of switches on the network.
C. the number of users on the network.
D. where network latency will occur.
第6题:
is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships:(67), the initiation of the successor activity, depends upon the completion of the predecessor activity.(68), the initiation of the successor activity, depends upon the initiation of the predecessor activity.
A.PDM
B.CPM
C.PERT
D.AOA
第7题:
Which IOS user EXEC command will allow a network technician to determine which router in the path to an unreachable network host should be examined more closely for the cause of the network failure?
A. EzonexamB> telnet
B. EzonexamB > ping
C. EzonexamB > trace
D. EzonexamB > show ip route
E. EzonexamB > show interface
F. EzonexamB > show cdp neighbors
第8题:
● The purpose of a dummy activity in an activity-on-arrow diagram is to:
A Identify a task that could be replaced by another.
B Take the slack time into account.
C Show a task that is not necessarily needed.
D Denote a milestone.
E Show a dependency relationship.
第9题:
the following diagram is() network topology structure
A.bus
B.star
C.ring
D.tree
第10题:
During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate This duration is what you commit to complete the project. What is wrong with the scenario? ()
A.The team did not create the estimate and estimating tales too long using that method
B.The team did not create the estimate and a network diagram was not used
C.The estimate is too long and should be created by management
D.The project estimate should be the same as the customer's required completion date