Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.A、PERTB、ResourcelevelingC、SchedulecompressionD、Critical chain method

题目

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.

  • A、PERT
  • B、Resourceleveling
  • C、Schedulecompression
  • D、Critical chain method
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

98 Which of the following tools and techniques can be used to collect information for the project closure reports?

A. Customer Surveys

B. Brainstorming

C. Document and Performance Analysis

D. Lessons Learned

E. All of the above


正确答案:E

第2题:

What you need is just a computer, because you can_____easily get on Internet.

A.many useful informations

B.much useful information

C.some useful informations

D.a lot of useful informations


参考答案:B

第3题:

●The standard (67) in C language contain many useful functions for input and output,string handling,mathematical computations,and system programming tasks.

(67) A.database

B.files

C.libraries

D.subroutine


正确答案:C
【解析】C语言当中的标准库包含很多有用的输入输出、字符串处理、数学计算和系统处理函数。

第4题:

The modern house has many useful electrical ____.

A.ambulances

B.equipments

C.mechanisms

D.appliances


答案:D

第5题:

Perform. Quality Control is the process of monitoring and recording resuks of executing the Quality Plan activities to assess performance and recommend necessary changes.( )are the techniques and tools in performing quality control. ①Activity network diagram②Cause and effect diagrams③Inspection④Flow chart⑤Work Breakdown Structure⑥Pareto chart A.①③⑤ B.②④⑤⑥ C.②③④⑤⑥ D.①②③④⑥


正确答案:D
执行质量控制是一个监督、评价项目质量计划活动执行结果和提出变更请求的过程。执行质量控制的技术和工具包括:活动网络图(Activity network diagram)、因果图(Cause and effect diagrams)、检查(Inspection)、流程图(Flow chart)和帕累托图(Pareto chart)等,但不包括工作分解结构(Work Breakdown Structure)。

第6题:

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.

A.PERT

B.Resourceleveling

C.Schedulecompression

D.Critical chain method


参考答案:D

第7题:

● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.

(72)

A.PERT

B.Resource levelling

C.Schedule compression

D.Critical chain method


正确答案:D
试题(72)分析
 在制定项目进度计划中有很多有用的方法和工具。如下:
 PERT方法能协调整个计划的各道工序,通过描绘出项目包含的各种活动的先后次序,标明每项活动的时间或相关的成本,合理安排人力、物力、时间、资金,加速计划的完成;
 Schedule compression进度压缩,是通过赶工、快速跟进等方法压缩工期,是在不改变项目范围条件下缩短项目进度的途径;
 Critical chain method关键路径法计算所有计划活动理论上的最早开始与完成时间、最迟开始与完成时间,寻找活动的关键路径,通过调整关键路径进行进度制定;
 Resource levelling资源平衡是根据有限资源调整项目进度的方法。
 所以选D。
参考答案
(72)D

第8题:

Which of the following tools and techniques can be used to collect information for the project closure reports?

A Customer Surveys

B Brainstorming

C Document and Performance Analysis

D Lessons Learned

E All of the above


正确答案:E

第9题:

According to Paul Leedy (1993: 17-42), which tools thatare useful for collecting a/the data are used by researchers?()

A.The Library

B.The Computer

C.Measurement

D.Statistics and Language


正确答案:ABCD

第10题:

Prior to the UML, there was no clearleading(66)Ianguage. Users had to choose from among many similar modeling languages with minor differences in overall(67)power. Most of the modeling languages shared a set of commonly accepted concepts that are expressed slightly differently in various languages. This lack of(68)discouraged new users from entering the OO market and from doing OO modeling, without greatly expanding the power of modeling. Users longed for the industry to adopt one, or a very few, broadly supported modeling languages suitable for(69)usage.

Some Vendors were discouraged from entering the OO modeling area because of the need to support many similar, but slightly different, modeling languages. In particular, the supply of add-on tools has been depressed because small vendors cannot afford to support many different formats from many differem(70)modeling tools. It is important to the entire OO industry to encourage broadly based tools and vendors, as well as niche products that cater to the needs of specialized groups.

A.programming

B.modeling

C.formal

D.intelligent


正确答案:B
解析:在UML出来之前,没有一个主流建模语言。用户必须在很多类似的,在整个表达能力上区别不大的建模语言中进行选择。大多数建模语言共享了一组被大众接受的概念,这些概念在不同的语言中只有细微的区别。这种缺乏一致性的现象,阻止了新的用户进入OO领域和进行OO建模,从而无法发挥建模的威力。用户渴望采用一个(或不多的几个)受广大支持的建模语言,适合于通用用途。因为要支持很多类似的,但有细小区别的建模语言,所以一些开发商不愿意进入OO建模领域。特别是add-on工具的供应在萎缩,因为小开发商负担不起支持很多的来自不同的前端建模语言的不同格式。广泛鼓励底层工具和开发商,以及能满足特殊群体需要的小批量产品,对进入OO工业是非常重要的。

更多相关问题