Using Job Scheduling Console, how can the external successor chain  be viewed when a job needs to be canceled?()A、 using the Hyperbolic ViewerB、 opening the Impact view and displaying the successorsC、 opening the Job Stream Instance editor for its Job Str

题目

Using Job Scheduling Console, how can the external successor chain  be viewed when a job needs to be canceled?()

  • A、 using the Hyperbolic Viewer
  • B、 opening the Impact view and displaying the successors
  • C、 opening the Job Stream Instance editor for its Job Stream Instance
  • D、 opening the Dependencies window and drilling down to the successors
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Which two statements are true about a job chain?()

A. A job chain can contain a nested chain of jobs.

B. The jobs in a job chain cannot have more than one dependency.

C. A job of the CHAIN type can be run using event-based or time-based schedules.

D. The jobs in a job chain can be executed only by using the events generated by the Scheduler


参考答案:A, C

第2题:

What is the danger associated with stopping a running job by using the STOP_JOB procedure?()

A. The job will need to be reenabled before it will execute again.

B. The job may hold locks on objects referenced within it.

C.All jobs within the job group will also be stopped.

D. The job may leave data in an inconsistent state.

E. There is no danger in using the STOP_JOB procedure.


参考答案:D

第3题:

Before sending your resume to prospective employers

or scheduling any interviews , you need to analyze the job market. Analyzing the job market involves determining actual job

openings and gathering information about organizations for which you want to work.


参考答案:在给目标雇主发简历或接受面试之前,你需要分析工作市场。分析工作市场需要你锁定实际的职位空缺,收集你想进入的机构的信息。

第4题:

Why is there no need to configure complex overlay network topologies when using Cisco WAAS? ()

  • A、remote scheduling of software distribution
  • B、comprehensive logs, reports, and graphs
  • C、automatic discovery of Cisco WAEs
  • D、content pre-positioning

正确答案:C

第5题:

You would be using mainly English in this job. Can you manage English conversation?


正确答案:
         

第6题:

Which of the following is true about job chains?()

A. They consist of one or more Scheduler programs.

B. They are used to implement dependency scheduling.

C. They are used to implement time-based scheduling.

D.They are used to implement event-based scheduling.

E.None of the above.


参考答案:B

第7题:

The user SYS creates a job by using the following command:Which two statements are true about the job that was created by the preceding command? ()(Choose two.)

A. The job is enabled by default after creation

B. The job is automatically dropped after the end date

C. The job executes with the privileges of the user SYS

D. The globalization environment that exists at the time of the job creation prevails at the job runs


参考答案:B, C

第8题:

The user SYS creates a job by using the following command:Which two statements are true about the job that was created by the preceding command?()

A. The job is enabled by default after creation

B. The job is automatically dropped after the end date

C. The job executes with the privileges of the user SYS

D.


参考答案:B, C

第9题:

How can a Job with EXEC as Internal Status be stopped in the Job Scheduling Console?()

  • A、 select Kill from the menu
  • B、 select Release from the menu
  • C、 select Cancel Job from the menu
  • D、 select Cancel Pending from the menu

正确答案:A

第10题:

Using the Tivoli Dynamic Workload Console, what are two ways to  change the priority of a job?()

  • A、 Open the "Set Priority" panel from the job properties.
  • B、 Change the priority of the job stream that contains the job.
  • C、 Select the corresponding action from the Monitor jobs task panel.
  • D、 Open the job stream properties and drill down to the job priority  panel.
  • E、 The priority of a job can only be changed from the Workload  Designer.

正确答案:A,C