Have the PDU requirements been met?
Are there sufficient KVM connections?
Is there sufficient service clearance?
Is there sufficient space in the existing rack?
第1题:
A customer has an 8-way p650 running an application for about 200 users. In the past, the requiredamount of memory and processors has increased proportionally to the number of new users. The customer plans to increase users by 10% each year for the next three years. Next year, a database will be added to the workload to support the users directly rather than being on a separate machine. What is the most likely result of this projected growth?()
第2题:
A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system. How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()
第3题:
A. The last policy is the default policy, which allows all traffic.
B. The order of policies is not important.
C. New policies are placed at the end of the policy list.
D. The insert command can be used to change the order.
第4题:
A customer server has the maximum local storage installed. The customer plans to share this new storage with other servers. Which of the following provides that server additional storage?()
第5题:
During a review of environmental requirements before ordering an IBM System z9 server and IBM System Storage DS8700, the customer states that the available power is 220 volts AC. Which feature should be included with the DS8700 order()
第6题:
Cisco.com offers account managers which three of these resources? ()
第7题:
A major account is considering migrating from a proprietary Unix server to a Linux and Intel-based platform. They are not sure if the Intel-based server will be able to handle the workload of the Unix server. What would be the best strategy to win with an IBM solution?()
第8题:
A customer has ordered a rack, a p650, two p630s, and two p615s. During a conversation on installation planning, the pSeries technical specialist recognizes that the customer expects the rack to arrive as one unit. However, the specialist knows that the p650 will be racked, but the other systems will arrive separately. In fact, the other systems are CSU (Customer Set Up). Why should the specialist immediately inform the customer that additional racking is the customer’s responsibility?()
第9题:
A customer is ordering a new p650 server to be placed into an existing OEM 42U 19-inch rack containing only two p630 servers. This is the first p650 in the enterprise. What is the most important question that the pSeries technical specialist should ask the customer before the order is placed?()
第10题:
A customer is looking for a new file and print server and is considering a 2-socket Intel server with redundant power and hard disk that must fit in the current server rack. With 2U available in the rack, the customer is looking for the best price performance ratio. Which IBM server will fit the best for this customer?()