Use AIX 5.3 which supports micro-partitioning for both the test and training LPARS
Use DLPAR to move resources from the test LPAR to training when training is active
Install Partition Load Manager to share resources between the test and training environments
Install Advanced Power Virtualization and then use micro-partitioning for both the test and training LPARs
第1题:
Companycom is installing a p5 595 with AIX 5.3. The DLPAR option for the resources cannot be selected on the HMC menus. However, the daemons are running on both the HMC and LPARs. Which of the following is a prerequisite for DLPAR functionality?()
第2题:
Companycom recently ordered a p5 570 and an HMC. Prior to delivery, two additional p5 570 servers were added to the order. Upon installation, the system administrator noticed that they do not have a method to connect the p5 570 servers to the HMC. Which of the following will allow them to connect all servers to the HMC?()
第3题:
Companycom has a requirement to consolidate six web application servers. There is unused capacity of 2 CPUs on their new p5 570. Which operating systems and or features are required?()
第4题:
Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()
第5题:
A p5 570 12 way was purchased with the plan to install six LPARs running AIX 5.2. The machine has 12 disks spread evenly over the internal server drawers. The customer would now like to add a seventh LPAR. Which of the following should be added for the seventh LPAR boot device?()
第6题:
Companycom is migrating from p670 systems running AIX 5.2 to p5 595 systems running AIX 5.3. They will be changing out only the system units. They will re-use the existing 61D drawers and adapters with the new p5 595 systems. What compatibility issue must be considered?()
第7题:
Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()
第8题:
A current Sun Solaris customer has just purchased their first p5 590. During the Solution Assurance, the backup requirements were discussed. Which of the following should be recommended to the customer with regards to restoring rootvg?()
第9题:
Companycom is migrating their application that was built on AIX 4.3, to a new p5 590 system that is running AIX 5.3. The application was a 32-bit program. What will need to be done with the application to allow it to run on the new system?()
第10题:
Companycom has a Linux LPAR on a p5 570 server. The 3rd party storage subsystem devices are not supported by Linux. How would access be provided to the storage subsystem devices for this Linux LPAR?()