CMS专题

单选题A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable in

题目
单选题
A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()
A

Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs

B

Move the existing physical network and storage adapters to the new system and virtualize the I/O using a  single VIO Server.

C

Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC  connectors and dual HBAs.

D

Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC  connectors and the other with dual HBAs.

如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

An administrator has set up three partitions using a shared processor pool with 2 processors and SMT turned on. The partitions are activated in the following sequence: Partition one: Min = 0.5, max = 3.0, desired = 1.0; Partition two: Min = 1.0, max = 3.0, desired = 1.5 Partition three: Min = 1, max = 0.5, desired = 2. What is the outcome?()

  • A、Partition one starts and has 3.0 logical processors. Partition two does not start. Partition three has 1.0 logical processors. 
  • B、Partition one starts and has 1.5 logical processors. Partition two has 1.0 logical processors. Partition three has 0.1 processors. 
  • C、Partition one starts and has 2.0 logical processors. Partition two start and has 2.0 logical processors. Partition three does not start. 
  • D、Partition one starts and has 2.0 logical processors. Partition two has 1.0 logical processors. Partition three has 0.1 logical processors.

正确答案:C

第2题:

Companycom is currently using a p690 and has just ordered a p5 590. They prefer to run in full system partition mode, since their application will utilize all the resources in the machine, and they don't want the overhead of an LPAR. What is the best response to the customer about the POWER5 capabilities?()

  • A、POWER5 runs in an SMP mode as default
  • B、POWER5 can run in a full system mode the same as the p690
  • C、POWER5 can run in full system mode with the purchase of PLM
  • D、POWER5 can run in a full system mode, but it is in LPAR mode

正确答案:D

第3题:

A customer has many RS/6000s and POWER4 systems running different AIX applications.  What should the customer do to best position themselves for the migration to POWER5?()

  • A、Upgrade OS to AIX 5.2.
  • B、Implement Micro-Partitioning.
  • C、Upgrade HMC to support POWER5.
  • D、Install Partition Load Manager.

正确答案:A

第4题:

A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()

  • A、 vmstat and iostat data from the older machines 
  • B、 The number of CPUs that were installed in the original machines 
  • C、 Data from Workload Estimator (WLE) and IBM Performance Management (PM) 
  • D、 Performance data that is collected from the new system after it has been put into production

正确答案:C

第5题:

A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()

  • A、Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs
  • B、Move the existing physical network and storage adapters to the new system and virtualize the I/O using a  single VIO Server.
  • C、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC  connectors and dual HBAs.
  • D、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC  connectors and the other with dual HBAs.

正确答案:C

第6题:

The systems administrator of a large manufacturer has POWER5 and POWER6 servers, each with LPARs running AIX 6.1.  They are running several workloads including SAP, DNS, Oracle, DB2 and WebSphere Application Server, and plan to consolidate onto one POWER7 server.   How can the system administrator determine how much benefit Active Memory Expansion (AME) could provide for the consolidated system?()

  • A、Run amepat now on all of the existing LPARs.
  • B、Run amepat after consolidation on all LPARs.
  • C、Run amepat now on all existing LPARs running on the POWER6 servers.
  • D、Run amepat now on all existing LPARs running database applications.

正确答案:A

第7题:

A customer has a Power 770 running an SAP ERP workload on AIX 7. It has a single partition with 12 cores and 48GB of memory and the CPU is underutilized at 46% with 1000 users. Memory utilization is at 80%. The number of users will increase to 1700, increasing memory utilization by 37%. Which of the following supports this requirement?()

  • A、Active Memory Server
  • B、Active Memory Sharing
  • C、Active Memory Pooling
  • D、Active Memory Expansion

正确答案:D

第8题:

A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server.  What is the minimum PowerVM edition that supports the customer requirement?()

  • A、 PowerVM Lx86
  • B、 PowerVM Express Edition
  • C、 PowerVM Standard Edition
  • D、 PowerVM Enterprise Edition

正确答案:C

第9题:

A customer has a requirement for a single AIX LPAR to be highly available. The customer only has enough funding to purchase a single system. Which would be the most critical option to mitigate AIX availability?()

  • A、Dual power supplies.
  • B、Twice the amount of disk.
  • C、Two dual-port LHEA adapters.
  • D、Two dual-port fibre channel adapters.

正确答案:A

第10题:

A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()

  • A、All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or later
  • B、The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HMC
  • C、They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based  systems connected to the existing one
  • D、The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM

正确答案:A