单选题An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?A Total float for the activi

题目
单选题
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
A

Total float for the activity is 9 days.

B

The early finish date ofthe activity is the end ofthe day on the 14th.

C

The late finish date is the 25th.

D

The activity can be completed in 2 days ifthe resources devoted to it are doubled.

如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:

A.Slack

B.Free float.

C.Restricted float.

D.Level float.

E.Lag


正确答案:E
E

第2题:

Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.

A . 11, 13

B . 12, 14

C . 13, 15

D . 14, 16

E . 15, 17


正确答案:E

第3题:

Which of the following is indicative of negative float?

A.The late start date is earlier than the early start date.

B.The critical path supports the imposed end date.

C.The early finish date is equal to the late finish date.

D.When leads are employed in the schedule.

E.The project is sinking.


正确答案:A
A

第4题:

117 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.

A. 11, 13

B. 12, 14

C. 13, 15

D. 14, 16

E. 15, 17


正确答案:E

第5题:

An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

A.Total float for the activity is 9 days.

B.The early finish date ofthe activity is the end ofthe day on the 14th.

C.The late finish date is the 25th.

D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.


参考答案:A

第6题:

Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.

A . 2, 10

B . 4, 12

C . 6, 14

D . 7, 15

E . 9, 17


正确答案:A

第7题:

22 The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:

A. Slack

B. Free float.

C. Restricted float.

D. Level float.

E. Lag


正确答案:E

第8题:

Free float is the amount of time that an activity may be delayed with out affecting the _____.

A.Early start of the succeeding activities.

B.Late start of the succeeding activities.

C.Project finish.

D.Cost of the project.

E.None of the above.


正确答案:A
A

第9题:

PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.

A.Finish-to-Start

B.Finish-to-Finish

C.Start-to-Start

D.Start-to-Finish


参考答案:D

该题的关键词为"PDM includes four types",其语句结构为"The completion of the successor activity(主语)depends upon(谓语)the initiation of the predecessor activity",含义为"后续活动的完成依赖于前置活动的开始",根据选项容易识别为SF活动依赖类型。

第10题:

119 Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.

A. 2, 10

B. 4, 12

C. 6, 14

D. 7, 15

E. 9, 17


正确答案:A