if the compass bearing of an approaching vessel does not appreciably change
even when an appreciable bearing change is evident, particularly when approaching a vessel at close range
if you observe both sidelights of a vessel ahead for an extended period of time
All of the above
第1题:
In Project Risk Management, Risk Response may include actions to:
A reduce the probability of risk events
B change the scope, budget, schedule or quality specifications of the project
C reduce the consequences or severity of impacts of a potential risk event
D A and C
E All of the above.
第2题:
In Project Risk Management, Risk Response may include actions to:
A. reduce the probability of risk events
B. change the scope, budget, schedule or quality specifications of the project
C. reduce the consequences or severity of impacts of a potential risk event
D. A and C
E. All of the above
第3题:
Which of the following does not contribute to increased Schedule Risk?
A labor shortage
B contractor claims
C lack of access
D sponsor scope changes
E all may increase schedule risk
第4题:
The risk of collision shall be deemed to exist if the compass bearing of an approaching vessel ().
A.did not appreciably change
B.does not appreciably change
C.do not appreciably change
D.not appreciably change
第5题:
Rule 14 describes the action to be taken by vessels meeting head-on. Which of the following conditions must exist in order for this rule to apply?______.
A.Both vessels must be power-driven.
B.They must be meeting on reciprocal or nearly reciprocal courses.
C.The situation must involve risk of collision.
D.All of the above
第6题:
144 Risk event probability is defined as:
A. the total number of possible events divided into the expectations or frequency of the risk event
B. the number of times the risk event may occur
C. the fraction of the total project tasks which may be affected by the risk event
D. the total number of possible events divided into the consequences of the risk event.
E. A and B
第7题:
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
A.share
B.Mitigate
C.Transfer
D.Acceptance
第8题:
Risk event probability is defined as:
A the total number of possible events divided into the expectations or frequency of the risk event
B the number of times the risk event may occur
C the fraction of the total project tasks which may be affected by the risk event
D the total number of possible events divided into the consequences of the risk event.
E A and B
第9题:
Risk of collision may exist ______.
A.if the compass bearing of an approaching vessel does NOT appreciably change
B.even when an appreciable bearing change is evident, particularly when approaching a vessel at close range
C.if you observe both sidelights of a vessel ahead for an extended period of time
D.All of the above
第10题:
You are running into danger,________.
A.shallow water ahead of you
B.submerged wreck ahead of you
C.risk of collision imminent
D.A,B,C are all right