第1题:

The schedule risk is the _____ .

A the accumulated "expected' durations which maintain project completion.

B Critical Path adjusted by "high-risk" activity float.

C highest risk path that maintains quality.

D Critical Path when calculated with "most likely" duration.

E highest risk path that contributes the most risk toward the project completion.


正确答案:B

第2题:

153 The range of time allowed for an activity to be completed in is the _____.

A. Planned time (Duration).

B. Float time (LS - ES, or LF - EF).

C. Critical time (when ES = LS, or EF = LF).

D. Scheduled time (LF - ES).

E. Event


正确答案:D

第3题:

The range of time allowed for an activity to be completed in is the _____.

A.Planned time (Duration).

B.Float time (LS - ES, or LF - EF).

C.Critical time (when ES = LS, or EF = LF).

D.Scheduled time (LF - ES).

E.Event.


正确答案:D
D

第4题:

As () machine tools, we regret to () that we are not able to supply for the time being.

A、regarded,say

B、regards,saying

C、regards,say

D、regarded,inform


参考答案:C

第5题:

● The range of time allowed for an activity to be completed in is the _____.

A Planned time (Duration).

B Float time (LS - ES, or LF - EF).

C Critical time (when ES = LS, or EF = LF).

D Scheduled time (LF - ES).

E Event.


正确答案:D

第6题:

112 The schedule risk is the _____ .

A. the accumulated "expected' durations which maintain project completion.

B. Critical Path adjusted by "high-risk" activity float.

C. highest risk path that maintains quality.

D. Critical Path when calculated with "most likely" duration.

E. highest risk path that contributes the most risk toward the project completion


正确答案:B

第7题:

35 The range of time allowed for an activity to be completed in is the _____.

A. Planned time (Duration).

B. Float time (LS - ES, or LF - EF).

C. Critical time (when ES = LS, or EF = LF).

D. Scheduled time (LF - ES).

E. Event.


正确答案:D

第8题:

Bar charts are most appropriate for:

A.Comparing actual to planned performance to each activity.

B.Showing slack time.

C.Showing critical path dependencies.

D.Showing which activities can be rearranged in parallel.

E.All of the above.


正确答案:A
A

第9题:

● Bar charts are most appropriate for:

A Comparing actual to planned performance to each activity.

B Showing slack time.

C Showing critical path dependencies.

D Showing which activities can be rearranged in parallel.

E All of the above.


正确答案:A

第10题:

What attention should be paid when bunkering oil in the USA?


正确答案:It is most complex and strict to bunker oil in the USA. Many rules are regulated in the port of USA. For instance, the oil man on the behalf of the ship submits preparation measures to harbour. Check all items in check list, by yes (√), no (×). According to the requirements, hoisting oil bunkering flag and plugging all sea valves are necessary. A bulletin written in "NO SMOKING" is ready for use. Stop loading or unloading operations on deck. Don