第1题:
The schedule risk is the _____ .
A the accumulated "expected' durations which maintain project completion.
B Critical Path adjusted by "high-risk" activity float.
C highest risk path that maintains quality.
D Critical Path when calculated with "most likely" duration.
E highest risk path that contributes the most risk toward the project completion.
第2题:
153 The range of time allowed for an activity to be completed in is the _____.
A. Planned time (Duration).
B. Float time (LS - ES, or LF - EF).
C. Critical time (when ES = LS, or EF = LF).
D. Scheduled time (LF - ES).
E. Event
第3题:
The range of time allowed for an activity to be completed in is the _____.
A.Planned time (Duration).
B.Float time (LS - ES, or LF - EF).
C.Critical time (when ES = LS, or EF = LF).
D.Scheduled time (LF - ES).
E.Event.
第4题:
As () machine tools, we regret to () that we are not able to supply for the time being.
A、regarded,say
B、regards,saying
C、regards,say
D、regarded,inform
第5题:
● The range of time allowed for an activity to be completed in is the _____.
A Planned time (Duration).
B Float time (LS - ES, or LF - EF).
C Critical time (when ES = LS, or EF = LF).
D Scheduled time (LF - ES).
E Event.
第6题:
112 The schedule risk is the _____ .
A. the accumulated "expected' durations which maintain project completion.
B. Critical Path adjusted by "high-risk" activity float.
C. highest risk path that maintains quality.
D. Critical Path when calculated with "most likely" duration.
E. highest risk path that contributes the most risk toward the project completion
第7题:
35 The range of time allowed for an activity to be completed in is the _____.
A. Planned time (Duration).
B. Float time (LS - ES, or LF - EF).
C. Critical time (when ES = LS, or EF = LF).
D. Scheduled time (LF - ES).
E. Event.
第8题:
Bar charts are most appropriate for:
A.Comparing actual to planned performance to each activity.
B.Showing slack time.
C.Showing critical path dependencies.
D.Showing which activities can be rearranged in parallel.
E.All of the above.
第9题:
● Bar charts are most appropriate for:
A Comparing actual to planned performance to each activity.
B Showing slack time.
C Showing critical path dependencies.
D Showing which activities can be rearranged in parallel.
E All of the above.