60 In a flowchart, the diamond form. is used to represent:

A. a starting point.

B. an operation.

C. a written report.

D. a decision point.

E. an end point


正确答案:D

第2题:

●ASCII is a 7-bit code used to represent numeric,alphabetic,and special printable characters.It also includes codes for control characters,which are (75) .

(75) A.printable or displayable

B.not printable or displayable

C.not printable but displayable

D.printable but not displayable


正确答案:B
【解析】ASCII是一种7比特编码,它用来表示数字、字符和特殊的打印符号。它也包含控制字符的编码,这些编码不能够打印或者显示。

第3题:

Work packages are used to:

A . Represent units of work at a level where work is performed.

B . Clearly distinguish one work package from all others assigned to a single functional group.

C . Limit the work to be performed to relatively short periods of time.

D . All of the above.

E . A and B only


正确答案:D

第4题:

An Intranet is(71)the application of Internet technology within an internal or closed user group.Internets are company(72)and do not have a(73)connection to the Internet.Used properly an Internet is highly effective corporate tool,capable of regularly(74)information to empower the workforce with the information needed to perform. their roles.Used in this way,Internet represent a step towards the(75)office.

(58)

A.simple

B.simply

C.single

D.singly


正确答案:B

第5题:

is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the logical relationships that exist between them. A.PERT B.AOA C.WBS D.PDM


正确答案:D
前导图法(PDM)用于关键路径法,是用于编制项目进度网络图的一种方法,它使用方框或者长方形(被称做节点)代表活动,它们之间用箭头连接,显示它们彼此之间存在的逻辑关系。

第6题:

148 Work packages are used to:

A. Represent units of work at a level where work is performed.

B. Clearly distinguish one work package from all others assigned to a single functional group.

C. Limit the work to be performed to relatively short periods of time.

D. All of the above.

E. A and B only


正确答案:D

第7题:

ASCII is a 7-bit code used to represent numeric, alphabetic, and special printable characters. It also includes codes for control characters, which are

A.printable or displayable

B.not printable or displayable

C.not printable but displayable

D.printable but not displayable


正确答案:B

第8题:

In a flowchart, the diamond form. is used to represent:

A . a starting point.

B . an operation.

C . a written report.

D . a decision point.

E . an end point.


正确答案:D

第9题:

The Abbreviation of Acrylonitrile Butadiene Styrene is ABS。()

此题为判断题(对,错)。


参考答案:√

第10题:

is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.

A.PERT

B.AOA

C.WBS

D.PDM


正确答案:D