第1题:
When all members must unanimously agree before a decision is reached
A all members become committed
B decisions are reached slowly
C integrity is developed
D future decision making ability is enhanced
E All of the above.
第2题:
● Configuration (baseline) control monitors performance against the
A scope baseline
B original schedule
C original budget
D All of the above.
E None of the above.
第3题:
A、of course
B、above all
C、for sure
D、not at all
第4题:
A.all in all
B.after all
C.first of all
D.above all
第5题:
A、management
B、creditors
C、investors
D、all of the above
第6题:
183 Configuration (baseline) control monitors performance against the
A. scope baseline
B. original schedule
C. original budget
D. All of the above.
E. None of the above
第7题:
● Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:
A The project manager
B The functional manager
C The project sponsor
D The client
E All of the above
第8题:
Communication plays a major role in:
A Planning
B Organizing
C Controlling
D Directing
E All of the above