IBM(000-237)

单选题A cluster node has a failed fibre adapter requiring the node to be halted to replace it. To minimize downtime, what is the appropriate method of performing this repair?()APerform the cIRGmove command to move the node’s resources to another cluster node

题目
单选题
A cluster node has a failed fibre adapter requiring the node to be halted to replace it. To minimize downtime, what is the appropriate method of performing this repair?()
A

 Perform the cIRGmove command to move the node’s resources to another cluster node.

B

 Perform a graceful stop of the cluster,replace the adapter,and restart the cluster.

C

 Perform a force stop of the cluster node,replace the adapter,and restart the cluster. 

D

 Perform a graceful takeover of the cluster,replace the adapter,and restart the cluster.

参考答案和解析
正确答案: A
解析: 暂无解析
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The en0 interface on Node1 of a two-node cluster has failed. This adapter is configured with a boot addressand under stable operations also has the service address of the cluster’s single resource group. The resourcegroup is configured with the fallback option. The HA network was configured for IPAT via aliasing and now theservice address is on the en1 interface in the cluster. The en0 interface has already been physically replacedand configured with the boot address. Which of the following will return the cluster to its original state andminimize cluster downtime?()

  • A、Run cluster synchronization.
  • B、Restart cluster services on Node1.
  • C、Perform a swap_adapter using C-SPOC
  • D、Restart cluster services on both nodes

正确答案:C

第2题:

A cluster node has a failed fibre adapter requiring the node to be halted to replace it. To minimize downtime, what is the appropriate method of performing this repair?()

  • A、 Perform the cIRGmove command to move the node’s resources to another cluster node.
  • B、 Perform a graceful stop of the cluster,replace the adapter,and restart the cluster.
  • C、 Perform a force stop of the cluster node,replace the adapter,and restart the cluster. 
  • D、 Perform a graceful takeover of the cluster,replace the adapter,and restart the cluster.

正确答案:D

第3题:

A new HACMP maintenance level has recently been released. An administrator is creating a  project plan that is required for applying the updates for a three-node production cluster.  To minimize downtime,what is the best way to accomplish the updates on all cluster nodes?()  

  • A、 Perform a graceful takeover one node at a time and apply the updates.
  • B、 Perform the updates on all nodes simultaneously using C-SPOC utilities.
  • C、 Perform the updates on node at a time with the cluster software active.
  • D、 Perform a graceful stop of all cluster nodes and apply updates to all nodes.

正确答案:A

第4题:

An administrator has a two node cluster, Node1 and Node2, running resource group rg1. The resource groupis active on Node1. The administrator stopped cluster services and unmanaged the resource group on Node1to work on a problem. Now the administrator needs to move rg1 to Node2. Which of the following will achievethis?()

  • A、Perform a clstart on Node1 with ’Manage Resource Groups’ set to ’Manually’ and select the destination ofNode2
  • B、Perform a resource group move operation from Node1 to Node2 and select the option to ’Re-manageResource Groups’ set to ’Automatically’
  • C、Perform a clstop on Node1 with option to move resource groups, this will release the resource group fromNode1 and accquire the resource group on Node2.
  • D、Perform a clstart on Node1 with ’Manage Resource Groups’ set to ’Automatically’, then perform a resourcegroup move operation to move rg1 from Node1 to Node2

正确答案:D

第5题:

What affect will a shutdown -Fr command have on the resource groups on a cluster node?()

  • A、 They will be placed in an error state.
  • B、 They will be released an not acquired by another node.
  • C、 They will migrate to the next node in the priority list.
  • D、 They will migrate to the next node and be reacquired by the first node on system restart.

正确答案:B

第6题:

During a cluster functionality test, and administrator performs a graceful stop for Node ’B’ in a three-node cluster. What is the expected state of the cluster after Node ’B’successfully completes?()  

  • A、 All cluster resources halt on Node ’B’,and one or both surviving nodes will gracefully acquire the resources.
  • B、 All cluster processes halt on Node ’B’,the cluster resources remain active,and the remaining  nodes take no action.
  • C、 All cluster processes stay active on Node ’B’,cluster resources are halted,and the remaining nodes take no action.
  • D、 All cluster resources will stop,cluster processes halt on Node ’B’,and the remaining cluster nodes take no action.

正确答案:D

第7题:

A three-node cluster experienced a node failure. The resource groups were acquired as cexpected. The node has been repaired,and HACMP has been restarted.  How does the operator determine that the node has successfully re-integrated into the cluster?()  

  • A、 Use the clstat command.
  • B、 Use the cIRGinfor command.
  • C、 Tail the /etc/hacmp.out file and wait for "node_up_complete" to finish successfully.
  • D、 Tail the /usr/es/adm/cluster.log file and wait for "node_up_complete" to finish successfully.

正确答案:A

第8题:

A customer has a resource group rg1 configured on a two node cluster with the following policies:The customer has observed the following scenarios as nodes join the cluster during cluster start up. Scenario 1 Node1 joins cluster as first node - rg1 is acquired by Node1 Node2 joins cluster as second node - rg1 ismoved from Node1 to Node2 Scenario 2 Node2 joins cluster as first node - rg1 is acquired by Node2 Node1 joins cluster as second node - rg1 remainson Node2 Which of the following is the reason for this behavior?()

  • A、rg1 is configured with a delayed fallback timer
  • B、Settling time policy has not been configured for rg1
  • C、Node1 does not have sufficient resources to support rg1
  • D、Node2 is the first in the ’Default Node Priority’ list for resource group rg1

正确答案:D

第9题:

A new administrator is performing fallover testing on a two-node cluster and is concerned that the cascading resource group belonging to Node ’A’ did not reintegrate properly after the cluster was restarted on Node ’A’. A stable cluster is reported by clstat,and clRGinfo reports the resource group online on Node ’B’.  What type of configuration would cause this type of behavior?()  

  • A、 The resource group DNP has been configured.
  • B、 The resource group option CWOF has been enabled.
  • C、 The resource group option Inactive Takeover is set.
  • D、 A resource group fallback timer has been configured.

正确答案:B

第10题:

A customer needs to test the failover capabilities of their cluster. Which of the following AIX commands, whenissued from the command line, will simulate a node crash and cause the cluster resource group running onthat server to fail over to another node?()

  • A、clstop
  • B、halt -q
  • C、shutdown -F
  • D、stopsrc -s cluster

正确答案:B

更多相关问题