Project acceptance
Scope verification
Scope definition
WBS Creation
第1题:
is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A.WBS Creation
B.Scope definition
C.Project acceptance
D.Scope verification
第2题:
is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A.Project acceptance
B.Scope verification
C.Scope definition
D.WBS Creation
第3题:
● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
(73)
A. work performance information
B. scope statement
C. change requests
D. process analysis
第4题:
A、project scope statement
B、work package
C、WBS
D、project scope plan
第5题:
The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
A.work performance information
B.scope statement
C.change requests
D.process analysis
第6题:
The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria
A.work performance information
B.scope statement
C.change requests
D.process analysis
第7题:
______describes,in detail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Stakeholder Analysis
D.The project scope statement
第8题:
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.
(74) A. Product scope description
B. Project objectives
C. Product specification
D. The project scope statement
第9题:
()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。
A、Validate scope
B、Define scope
C、Control scope
D、Collect requirement
第10题:
is the process of obtaining the stakeholdrs' formal acceptance of the completed project Scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A.Project acceptance
B.Scope verification
C.Scope definition
D.WBS Creation