单选题Which of the following lists of items all require an HMC to function with POWER5?()A Running AIX 5.3 Implementing HACMP Implementing Static LPARB Implementing Advanced POWER Virtualization Running Linux Attaching RIO drawersC Implementing VIO Server Im

题目
单选题
Which of the following lists of items all require an HMC to function with POWER5?()
A

Running AIX 5.3 Implementing HACMP Implementing Static LPAR

B

Implementing Advanced POWER Virtualization Running Linux Attaching RIO drawers

C

Implementing VIO Server Implementing Dynamic LPAR Running with SMT turned On

D

Running AIX and Linux on the same system Implementing CoD Implementing Micro-Partitioning

如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Companycom is installing a p5 595 with AIX 5.3. The DLPAR option for the resources cannot be selected on the HMC menus. However, the daemons are running on both the HMC and LPARs. Which of the following is a prerequisite for DLPAR functionality?()

  • A、The resources must be unallocated in an LPAR
  • B、The microcode on the pSeries must be current
  • C、All network adapters on the LPAR must be defined
  • D、Network connectivity and name resolution capability between HMC and LPARs

正确答案:D

第2题:

A customer wishes to replace 12 older small UNIX systems.  They are running out of floor space in their data center and any solution must take this into consideration.  Assuming that the applications are supported on all AIX versions, which of the following would best meet the customer’s requirements?()

  • A、A p650 running AIX v5.3
  • B、A p5-550 running AIX v5.3
  • C、A p5-570 running Advanced POWER Virtualization
  • D、Multiple rack-mounted p615s running dynamic LPAR

正确答案:C

第3题:

In addition to a POWER5 system and an HMC, what else is required to enable Micro-Partitions in an AIX environment?()

  • A、AIX 5.3 and Dynamic Logical Partitioning
  • B、AIX 5.2 and Dynamic Logical Partitioning
  • C、AIX 5.2 and Advanced POWER Virtualization feature
  • D、AIX 5.3 and Advanced POWER Virtualization feature

正确答案:D

第4题:

Companycom currently has three p650 servers in their environment and they are implementing a p5 595. The p650 servers are running in an SMP environment, but are connected to a pair of HMCs. In order to follow best practices in the enterprise server environment and maintain HMC connectivity to the p650s, what else will needs to be ordered in addition to the p5 595?()

  • A、Include a new HMC in the order to connect to the p5 595
  • B、Include a pair of new HMCs in the order to connect to the p5 595
  • C、Include a media set for POWER5 HMC in the order to upgrade one of the existing HMC’s to POWER5 capabilities
  • D、Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC to  POWER5 capabilities Include a media set for POWER5 HMC in the order to upgrade both of the existing HMC? To POWER5 capabilities

正确答案:B

第5题:

A customer wants to take advantage of IBM’s Micro-Partitioning capabilities for their new AIX applications.   The pSeries technical specialist should recommend purchasing which of the following?()

  • A、p5 hardware, AIX 5.2, Virtual I/O Server
  • B、POWER4 hardware, AIX 5.3, Virtual I/O Server,
  • C、p5 hardware, AIX 5.3, Advanced POWER Virtualization feature
  • D、POWER4 hardware, AIX 5.2, Advanced POWER Virtualization feature

正确答案:C

第6题:

During implementation of a two-node cluster,it is determined that error notification for the shared Disk subsystem would be beneficial.  Which of the following is a pre-requisite for implementing automatic error notification?()  

  • A、 The cluster must not be running.
  • B、 The cluster.es.server.utils lpp must be installed.
  • C、 The error notification module must be enabled in RSCT.
  • D、 The permissions on /tmp/hacmp.out need to be changed to 774.

正确答案:A

第7题:

Which of the following is required to use Simultaneous Multi-Threading (SMT)?()

  • A、smtctl command
  • B、A dual core chip
  • C、AIX 5.3 operating system and POWER5 hardware
  • D、Advanced Virtualization which is a separately purchased product

正确答案:C

第8题:

An administrator is implementing a second server due to the increased usage. Which of the following optimization techniques is the administrator using?()

  • A、Caching engines
  • B、QoS
  • C、Traffic shaping
  • D、Load balancing

正确答案:D

第9题:

An IT director is eager to adopt POWER7 servers because of their relative performance ratings and energy efficiency, but is concerned about migrating applications which require AIX 5.3. Which of the following will address his concern?()

  • A、POWER7 servers running AIX 5.3 operate in POWER5+ mode.
  • B、POWER7 servers running AIX 5.3 operate in POWER6 and POWER6+ mode.
  • C、POWER7 servers running AIX 5.3 operate in POWER5 and POWER6 modes.
  • D、POWER7 servers running AIX 5.3 operate in POWER6 and POWER7 modes.

正确答案:B

第10题:

Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()

  • A、Upgrade the p690 to a p5 590 server running AIX 5.3
  • B、Upgrade the p690 server to AIX 5.3 and implement Advanced Power Virtualization
  • C、Purchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adapters
  • D、Purchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization

正确答案:D