单选题Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recomm

题目
单选题
Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()
A

Use the 60 Amp line cords

B

Change the 100 Amp connector to a 60 Amp circuit

C

Submit an RPQ to order the p5 590 with 100 Amp power cords

D

Change the configuration and order the p5 590 with the 100 Amp power cords

参考答案和解析
正确答案: B
解析: 暂无解析
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A customer wants to take advantage of IBM’s Micro-Partitioning capabilities for their new AIX applications.   The pSeries technical specialist should recommend purchasing which of the following?()

  • A、p5 hardware, AIX 5.2, Virtual I/O Server
  • B、POWER4 hardware, AIX 5.3, Virtual I/O Server,
  • C、p5 hardware, AIX 5.3, Advanced POWER Virtualization feature
  • D、POWER4 hardware, AIX 5.2, Advanced POWER Virtualization feature

正确答案:C

第2题:

Companycom has a p690 server with unused fiber (HBA) host bus adapters (feature code 6228) that they would like to reuse. They are interested in implementing Advanced Power Virtualization features particularly Virtual IO. What is the best way to proceed?()

  • A、Upgrade the p690 to a p5 590 server running AIX 5.3
  • B、Upgrade the p690 server to AIX 5.3 and implement Advanced Power Virtualization
  • C、Purchase a p5 590 with minimum resources and simply reuse the p690 unused fiber HBA adapters
  • D、Purchase a p5 590 that has all the needed resources and adapters for Advanced Power Virtualization

正确答案:D

第3题:

Companycom is purchasing a p5 595 as part of a large server consolidation. They are planning on using micropartitioning and Virtual IO to consolidate small machines. They used the rPerf numbers for AIX 5.3 to size their solutions. They discovered that their application is not yet certified on AIX 5.3, so they will have to use AIX 5.2. What changes should be made to their configuration?()

  • A、Increase memory
  • B、Add more adapters
  • C、Increase both processors and adapters
  • D、Increase the number of processors by 20 - 30%

正确答案:C

第4题:

A client has an existing p5 570 that is directly connected to a HMC. The customer will be purchasing another p5 570. Which of the following solutions would be appropriate to provide HMC connectivity to the second p5 570?()

  • A、Implement a proxy server to provide multiple sources to one destination 
  • B、Purchase an additional Ethernet adapter for each p5 570 to provide connectivity between the two 
  • C、Purchase a network hub or switch so both p5 570s can connect to the single HMC 
  • D、Purchase an additional HMC since multiple HMC are required when more than one POWER5 Enterprise class server is used Purchase an additional HMC since multiple HMC? are required when more than one POWER5 Enterprise class server is used

正确答案:C

第5题:

Companycom wants the application server LPAR to communicate with the database LPAR on a p5 590 without using network adapters. What does the customer need to install?()

  • A、VIO Server
  • B、AIX 5.2 ML4
  • C、Shared Ethernet Adapter
  • D、AIX 5.3 with Advanced Power Virtualization

正确答案:D

第6题:

Companycom is currently using a p690 and has just ordered a p5 590. They prefer to run in full system partition mode, since their application will utilize all the resources in the machine, and they don't want the overhead of an LPAR. What is the best response to the customer about the POWER5 capabilities?()

  • A、POWER5 runs in an SMP mode as default
  • B、POWER5 can run in a full system mode the same as the p690
  • C、POWER5 can run in full system mode with the purchase of PLM
  • D、POWER5 can run in a full system mode, but it is in LPAR mode

正确答案:D

第7题:

Companycom is purchasing a 64-way p5 595. They have determined the location for the server is in a datacenter which does not have a raised floor. Which of the following would best meet the server requirements?()

  • A、The server must be installed into a location with a raised floor for optimum system cooling  and cable management.
  • B、The server should be purchased as a p5 590 and then upgraded to a p5 595. This will eliminate the need for a raised floor environment.
  • C、The server should be purchased as 32-way p5 595 and then upgraded to a 64-way. This will eliminate the need for a raised floor environment.
  • D、The server can be installed into a location without a raised floor if an RPQ is obtained. It is a strong IBM recommendation for a raised floor, not a requirement.

正确答案:A

第8题:

Companycom is considering a partitioned solution which will require cumulative rPerf total of 150. The original sizing came back recommending a 32-way p5 590. However, they have a requirement for future scalability and availability is important. Which of the following would be the best reason to recommend a p5 595?()

  • A、The p5 595 would allow for COD
  • B、The p5 595 includes the Advanced Power Virtualization hardware and software
  • C、The p5 595 is priced the same as the p5 590 given the same number/type of CPUs
  • D、The p5 595 performance would be equivalent to the p5 590 given the same number/type of CPUs

正确答案:A

第9题:

Companycom has successfully established their p5 LPAR environment on a POWER5 p5 590 running AIX 5.2. They are now ready to move to Virtual IO. What would be required to do Virtual IO?()

  • A、Apply APAR IY62262 to the current AIX 5.2 Maintenance level 04. Virtual IO Server is not required. 
  • B、Purchase Advanced POWER Virtualization software, upgrade to AIX 5.3 maintenance level 1 and apply APAR IY60349. Virtual IO Server is not required. 
  • C、Verify that there are enough resources to add a Virtual IO Server, upgrade to AIX 5.3 with APAR IY60349, create a Virtual IO Server after applying APAR IY62262. 
  • D、Verify that there are enough resources to add a Virtual IO Server, create a Virtual IO Server and apply APAR IY62262, verify that the system is at AIX 5.2 with Maintenance level 04.

正确答案:C

第10题:

Companycom is purchasing a p5 590 which was configured with 60 Amp line cords. They have just indicated that their large datacenter is already wired for 100 Amp power circuits in the location where the server will be installed. What would be the recommended action?()

  • A、Use the 60 Amp line cords
  • B、Change the 100 Amp connector to a 60 Amp circuit
  • C、Submit an RPQ to order the p5 590 with 100 Amp power cords
  • D、Change the configuration and order the p5 590 with the 100 Amp power cords

正确答案:D