A project management technique that is currently in widespread use is the(71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities call

题目

A project management technique that is currently in widespread use is the(71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called(72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide(73), whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management.(74) was developed to make clear the interdependence between project tasks before those tasks are scheduled.(75) offers the advantage of clearly showing overlapping tasks.

A.Structure Chart

B.Organizational Structure

C.Work Breakdown Structure

D.Functional decomposition diagram

如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

●Object-oriented analysis (OOA) is a semiformal specification technique for the object-oriented paradigm. Object-oriented analysis consists of three steps. The first step is (71). It determines how the various results are computed by the product and presents this information in the form. of a (72) and associated scenarios. The second is (73) , which determines the classes and their attributes, then determines the interrelationships and interaction among the classes. The last step is (74) , which determines the actions performed by or to each class or subclass and presents this information in the form. of (75) .

(71)

A.use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(72)

A. collaboration diagram

B. sequence diagram

C. use-case diagram

D. activity diagram

(73)

A. use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(74)

A.use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(75)

A. activity diagram

B. component diagram

C. sequence diagram

D. state diagram


正确答案:A,C,B,C,D

第2题:

Currently 94% of Web users use either Internet Explorer or Firefox, but recently some new(71) have been developed that are beginning to attract attention. The browser Opera is becoming very(72) because of its speed, it is currently the world's fastest browser, and because it is much smaller(73) existing browsers (it can almost fit on a single diskette). It can also(74) the last Web page you visited, so the next time you surf, you can start where you left off. And like the big two, you can get it for free; the catch is that you have to watch blinking ads in one comer, or pay $40 for the ad-free (75) of Opera.

A.readers

B.machines

C.techniques

D.browsers


正确答案:D

第3题:

● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.

(71)

A.risk

B.problem

C.result

D.data


正确答案:A

第4题:

Currently 94% of Web users use either Internet Explorer or Firefox, but recently some new (71) have been developed that are beginning to attract attention. The browser Opera is becoming very(72)because of its speed, it is currently the world’s fastest browser, and because it is much smaller(73) existing browsers (it can almost fit on a single diskette). It can also (74)the last Web page you visited, so the next time you surf, you can start where you left off. And like the big two, you can get it for free; the catch is that you have to watch blinking ads in one corner, or pay $40 for the ad-free (75) of Opera.

A.beyond
B.so
C.than
D.as

答案:C
解析:
参考译文:目前,有94%的网络用户使用Internet Explorer或firefox浏览器,但最近也开发出了一些新的浏览器,并吸引了用户的注意。Opera浏览器现在变得非常受欢迎,因为它是目前世界上速度最快的浏览器,也因为它远小于现存浏览器(它几乎可以存放在一个单一的软盘)。它可以记住上次访问过的网页,因此当你下次上网时,它会从这一页面开始。和两个主流的浏览器一样,你也可以免费使用Opera,只不过你必须观赏角落里的广告,或支付40美元来获得没有广告的Opera版本。

第5题:

_________________

A. ideas B. ambitious C. achievement D. technique


正确答案:A

第6题:

Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.

A.risk

B.problem

C.result

D.data


正确答案:A
风险是一个不确定因素或条件,如果它一旦发生,可能对至少一个项目目标,如项目进度、项目成本、项目范围或项目质量产生负面或正面的影响。选项A是风险,选项B是问题,选项C是结果,选项D是数据。根据项目风险定义,风险包括两方面含义:一是未实现目标;二是不确定性。因此应选择A。

第7题:

Project (75).Management:includes the processes required to ensure that the project includes au the word required, and only the work required, to complete the project successfully.

A.Integration

B.Configuration

C.Scope

D.Requirement


正确答案:C

第8题:

试题(71)~(75)Object-oriented analysis (OOA) is a semiformal specification technique for the object-oriented paradigm. Object-oriented analysis consists of three steps. The first step is (71). It determines how the various results are computed by the product and presents this information in the form. of a (72) and associated scenarios. The second is (73) , which determines the classes and their attributes. Then determine the interrelationships and interaction among the classes. The last step is (74) , which determines the actions performed by or to each class or subclass and presents this information in the form. of (75) .

(71)

A. use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(72)

A. collaboration diagram

B. sequence diagram

C. use-case diagram

D. activity diagram

(73)

A. use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(74)

A. use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling(75)

A. activity diagram

B. component diagram

C. sequence diagram

D. state diagram


正确答案:A,C,B,C,D

参考译文
面向对象的分析(OOA)是一种面向对象范型的半形式化描述技术。面向对象的分析包括3个步骤:第1步是用例建模,它决定了如何由产品得到各项计算结果,并以用例图和相关场景的方式展现出来;第2步是类建模,它决定了类及其属性,然后确定类之间的关系和交互;第3步是动态建模,它决定了类或每个子类的行为,并以状态图的形式进行表示。

第9题:

● Object-oriented analysis (OOA) is a semiformal specification technique for the object-oriented paradigm. Object-oriented analysis consists of three steps. The first step is (71). It determines how the various results are computed by the product and presents this information in the form. of a (72) and associated scenarios. The second is (73) , which determines the classes and their attributes. Then determine the interrelationships and interaction among the classes. The last step is (74) , which determines the actions performed by or to each class or subclass and presents this information in the form. of (75) .

(71)

A.use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(72)

A. collaboration diagram

B. sequence diagram

C. use-case diagram

D. activity diagram

(73)

A. use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(74)

A.use-case modeling

B. class modeling

C. dynamic modeling

D. behavioral modeling

(75)

A. activity diagram

B. component diagram

C. sequence diagram

D. state diagram


正确答案:A,C,B,C,D

第10题:

technique