软考中级

The (74) technique involves using project characteristics in a mathematical model to predict total project cost models Can be simple or complex.A.reserve analysisB.cost aggregationC.parametric estimatingD.funding limit reconciliation

题目

The (74) technique involves using project characteristics in a mathematical model to predict total project cost models Can be simple or complex.

A.reserve analysis

B.cost aggregation

C.parametric estimating

D.funding limit reconciliation

如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The plan ()the cooperation of young and old.

A. puts

B. keeps

C. gets

D. involves

知识点: Newassignment1


参考答案: D

第2题:

Whichinformationisrequiredtogetthefeatureactivationcodes()

A.machineserialnumber,model,andmachinesignature

B.model,disksize,andmachineserialnumber

C.model,StorageManagerversion,andmachinesignature

D.model,WWNN,andmachineserialnumber


参考答案:A

第3题:

● Project (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

A.Integration

B.Time

C.Planning

D.Communication


正确答案:D

第4题:

The committee comprises five persons.

A:.absorbs
B: concerns
C: excludes
D: involves

答案:D
解析:
句意为:委员会由五个人组成。画线单词comprise意为“包含,由……组成”。absorb 意为“吸收”;concern意为“关注”;exclude意为“排除”;involve意为“包含”。根据画线单词意思,只有involve与其同义,可进行替换。因此D项正确。

第5题:

Project(74)Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

A.Integration

B.Time

C.Planning

D.Communication


正确答案:D
解析:项目沟通管理是使用所需过程以确保及时、恰当地产生、收集、分发、存储、收回和最终处置项目信息的知识域。

第6题:

analysis emphasizes the drawing of pictorial system models to document and validate both existing and/or proposed systems. Ultimately, the system models become the(72)for designing and constructing an improved system.(73)is such a technique. The emphasis in this technique is process-centered. Systems analysts draw a series of process models called(74).(75)is another such technique that integrates data and process concerns into constructs called objects.

A.Prototyping

B.Accelerated

C.Model-driven

D.Iterative


正确答案:C

第7题:

_________________

A. ideas B. ambitious C. achievement D. technique


正确答案:A

第8题:

The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


正确答案:A
风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

第9题:

The manager spoke highly of such characters as loyalty,courage and truthfulness shown by his employees.

A:virtues
B:features
C:properties
D:characteristics

答案:A
解析:
经理高度赞扬他的员工表现出的一些优良品德,如忠诚、有勇气和诚实。 virtue“美德、优点”,最符合题意,例如:Virtue is fairer far than beauty.美德远胜于美貌。feature “特色”,例如:The spacious gardens are a special feature of the property.宽广的花园是该住宅区的一个特色。property“属性”,例如:A radio signal has both electrical and magnetic properties.无线电信号有电和磁两种特性。characteristic“特征”,例如:Ambition is a characteristic of all successful businessmen.雄心勃勃是所有成功生意人的共同特点。

第10题:

technique