Risk management’s ( ) is to assure uncertainty does not deflect the endeavor from the business.A.trendB.detailC.objectiveD.rule

题目

Risk management’s ( ) is to assure uncertainty does not deflect the endeavor from the business.

A.trend

B.detail

C.objective

D.rule

参考答案和解析
正确答案:C
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The Utility Theory _____ .

A considers risk propensity of the decision maker.

B attempts to formalize management's risk considerations.

C works well with decision tree analysis.

D is considered highly theoretical.

E All of the above.


正确答案:B

第2题:

Which phase of the project life cycle typically has the highest uncertainty and risk associated with it?

A concept

B development

C execution

D conclusion

E All of the above.


正确答案:A

第3题:

Risk mitigation is the process of _____ .

A transferring risk to another party.

B reducing uncertainty on the project

C identifying all possible risk events

D monitoring status and making adjustments

E All of the above.


正确答案:B

第4题:

186 Risk management requires an understanding that _____ .

A. the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.

B. risk identification must be directly aligned with the Work Breakdown Structure.

C. it is merely advanced preparation for possible adverse future events.

D. it does not imply complete control of events

E. All of the above


正确答案:E

第5题:

157 Sensitivity analysis can be used in risk analysis to:

A. Substitute for uncertainty analysis in risk quantification

B. estimate the level of risk aversion adopted by management

C. estimate the effect of change of one project variable on the overall project

D. A and B

E. All of the above


正确答案:C

第6题:

Sensitivity analysis can be used in risk analysis to:

A Substitute for uncertainty analysis in risk quantification

B estimate the level of risk aversion adopted by management

C estimate the effect of change of one project variable on the overall project

D A and B

E All of the above.


正确答案:C

第7题:

The highest degrees of project risk and uncertainty are associated with the following phase of the project:

A conceptual

B execution

C cut-over

D post project evaluation

E A and D only


正确答案:A

第8题:

Risk management requires an understanding that _____ .

A the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.

B risk identification must be directly aligned with the Work Breakdown Structure.

C it is merely advanced preparation for possible adverse future events.

D it does not imply complete control of events

E All of the above.


正确答案:E

第9题:

60 The Utility Theory _____ .

A. considers risk propensity of the decision maker.

B. attempts to formalize management's risk considerations.

C. works well with decision tree analysis.

D. is considered highly theoretical.

E. All of the above


正确答案:B

第10题:

26 Risk mitigation is the process of _____ .

A. transferring risk to another party.

B. reducing uncertainty on the project

C. identifying all possible risk events

D. monitoring status and making adjustments

E. All of the above.


正确答案:B