软考中级

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress. A.scope statement B.activity list C.project charter D.project schedule

题目

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress. A.scope statement B.activity list C.project charter D.project schedule

参考答案和解析
正确答案:D
制定进度表可能要求对历时估算与资源估算进行审查与修改,以便进度表在批准之后能够当做跟踪项目绩效的基准使用。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

130 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.

A. Conceptual, charter/baseline.

B. Conceptual, master schedule.

C. Development, charter/baseline.

D. Development, master schedule.

E. Development, masterplan


正确答案:A

第2题:

2 The Work Breakdown Structure (WBS) is the basis for communicating:

A. Project scope, cost control, schedule, quality

B. Project objectives, dependencies, plan, cost control

C. Project scope, schedule, staffing, cost control

D. Project scope, quality, schedule, dependencies

E. Project budget, schedule, risk factors, work assignments


正确答案:A

第3题:

The Work Breakdown Structure (WBS) is the basis for communicating:

A.Project scope, cost control, schedule, quality

B.Project objectives, dependencies, plan, cost control

C.Project scope, schedule, staffing, cost control

D.Project scope, quality, schedule, dependencies

E.Project budget, schedule, risk factors, work assignments.


正确答案:A
A

第4题:

以下调用宏定义的方法哪个是正确的?

A.const userUrl = require(‘../../config.js’).userUrl

B.userUrl = require(‘../../config.js’).userUrl

C.const userUrl = (‘../../config.js’).userUrl

D.const userUrl = require(‘../../config.js’)


const userUrl = require(‘../../config.js’).userUrl

第5题:

● The Work Breakdown Structure (WBS) is the basis for communicating:

A Project scope, cost control, schedule, quality

B Project objectives, dependencies, plan, cost control

C Project scope, schedule, staffing, cost control

D Project scope, quality, schedule, dependencies

E Project budget, schedule, risk factors, work assignments.


正确答案:A

第6题:

120 The Work Breakdown Structure (WBS) is the basis for communicating:

A. Project scope, cost control, schedule, quality

B. Project objectives, dependencies, plan, cost control

C. Project scope, schedule, staffing, cost control

D. Project scope, quality, schedule, dependencies

E. Project budget, schedule, risk factors, work assignments


正确答案:A

第7题:

12 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.

A. Conceptual, charter/baseline.

B. Conceptual, master schedule.

C. Development, charter/baseline.

D. Development, master schedule.

E. Development, masterplan


正确答案:A

第8题:

The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.

A.Conceptual, charter/baseline.

B.Conceptual, master schedule.

C.Development, charter/baseline.

D.Development, master schedule.

E.Development, masterplan.


正确答案:A
A

第9题:

Asystemadministratorhasbeenaskedtomigratethedev_vgvolumegroupfromserverAtoserverB.Thedev_vgvolumegroupcontainsasinglefilesystemnamed"/development".Toprepareformigration,whichofthefollowingisthecorrectsequenceofcommandsforremovingthevolumegroupfromserverA?()

A.exportvgdev_vg;umount/development;varyoffvgdev_vg

B.varyoffvgdev_vg;umount/development;exportvgdev_vg

C.umount/development;exportvgdev_vg;varyoffvgdev_vg

D.umount/development;varyoffvgdev_vg;exportvgdev_vg


参考答案:D

第10题:

增加Review数量和提高Review评级可以实现广告优化。


注意力;品牌联系;说服力