第1题:
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.
(74)
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第2题:
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.
(74) A. Product scope description
B. Project objectives
C. Product specification
D. The project scope statement
第3题:
A.project scope statement
B.project requirement
C.project charter
D.product specification
第4题:
Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement
第5题:
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第6题:
● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.
t
A.Integration
B.Scope
C.Configuration
D.Requiremen
第7题:
is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A.WBS Creation
B.Scope definition
C.Project acceptance
D.Scope verification
第8题:
A An organization oriented family tree of the project.
B A task oriented family tree of the project.
C A cost centered structure of the project.
D Only required on large complex projects where separately identifiable work packages are difficult to construct.
E None of the above.
第9题:
______describes,in detail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Stakeholder Analysis
D.The project scope statement
第10题:
A、project scope statement
B、work package
C、WBS
D、project scope plan