()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included

题目
()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.

A. Create scopE
B. Project stakeholder management
C. Project scope management
D. Project cost management
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.

(74)

A.Develop Schedule

B.Estimate Activity Resources

C.Define Activities

D.Sequence Activities


正确答案:A
试题(74)分析
    项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。
参考答案
    (74)A

第2题:

●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.

(74) A. Product scope description

B. Project objectives

C. Product specification

D. The project scope statement


正确答案:D

第3题:

The()describes, in detail, the project's deliverables and the work required to create those deliverables.

A.project scope statement

B.project requirement

C.project charter

D.product specification


参考答案:A

第4题:

Project (24) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

A.Integration

B.Scope

C.Configuration

D.Requirement


正确答案:B
解析:项目范围管理包括为确保项目包含且仅包含成功完成项目必需工作的所需过程。

第5题:

Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

A.Develop Schedule

B.Estimate Activity Resources

C.Define Activities

D.Sequence Activities


正确答案:A
解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。

第6题:

● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.

t

A.Integration

B.Scope

C.Configuration

D.Requiremen


正确答案:B

第7题:

is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

A.WBS Creation

B.Scope definition

C.Project acceptance

D.Scope verification


正确答案:D

第8题:

A An organization oriented family tree of the project.

B A task oriented family tree of the project.

C A cost centered structure of the project.

D Only required on large complex projects where separately identifiable work packages are difficult to construct.

E None of the above.


正确答案:B

第9题:

______describes,in detail,the project's deliverables and the work required to create those deliverables.

A.Product scope description

B.Project objectives

C.Stakeholder Analysis

D.The project scope statement


正确答案:D
解析:项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。
选项A是产品范围说明书,选项B是项目目标,选项C是干系人分析,选项D是项目范围说明书。故D是正确的。

第10题:

The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

A、project scope statement

B、work package

C、WBS

D、project scope plan


参考答案:C