( )is not included in Perform Integrated Change Control Process.A.Defining subsidiary plans B.Approving changes C.Managing changes to deliverables D.Reviewing all change requests

题目
( )is not included in Perform Integrated Change Control Process.

A.Defining subsidiary plans
B.Approving changes
C.Managing changes to deliverables
D.Reviewing all change requests
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● The purpose of configuration management is to:

A insure drawings are updated

B control change throughout the project

C control change during the production only

D generate engineering change proposals

E inform. the project manager of changes


正确答案:B

第2题:

The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)

A.change control board

B. project management office

C.project manager

D.configuration management officer


正确答案:C
本题目翻译:实施整体变更控制过程是从项目开始到完成进行,是项目经理的摄终责任。考察的是整体变更管理。

第3题:

The purpose of configuration management is to:

A.insure drawings are updated

B.control change throughout the project

C.control change during the production only

D.generate engineering change proposals

E.inform. the project manager of changes


正确答案:B
B

第4题:

The perform Integrated Change Contorl process is the uitimste responsbilityof the(请作答此空),Although changes my be intitated verbally,y they should be recorded in writtern form and entered into the( )syste.

A.resource sanager
B.division sanager
C.functional manager
D.projeet manager

答案:D
解析:
执行综合变更控制过程是(73)的首要责任,尽管口头上对变更进行了说明,但它们应以书面形式记录并输入(74)系统。(73)A.资源管理员B.部门经理C.职能经理D.项目经理
(74)A.质量管理B.配置管理C.风险管理D.范围管理

第5题:

The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .实施整体变更控制过程是从项目开始到项目结束并且是( )项目经理的最终责任。

A.Chang control board变更控制委员会
B.Project management office项目管理办公室
C.Project manager项目经理
D.Configuration management officer配置管理员

答案:C
解析:

第6题:

The perform. Integrated Change Contorl process is the ultimate responsibility of the(①).Although changes may be initiated verbally,they should be recorded in writtern form. and entered into the (②)system.

①A.resource manager

B.division manager

C.functional manager

D.project manager

②.A.quality management

B.configuration management

C.project manager

D.scope management


参考答案:D,D

第7题:

The perform Integrated Change Contorl process is the uitimste responsbilityof the (请作答此空) ,Although changes my be intitated verbally,they should be recorded in writtern form and entered into the ( ) syste.

A.resource manager
B.division manager
C.functional manager
D.projeet manager

答案:D
解析:
翻译:执行综合变更控制过程是(请作答此空)的首要责任,尽管口头上对变更进行了说明,但它们应以书面形式记录并输入( )系统。A. 资源管理员B. 部门经理C. 职能经理D. 项目经理

第8题:

33 The purpose of configuration management is to:

A. insure drawings are updated

B. control change throughout the project

C. control change during the production only

D. generate engineering change proposals

E. inform. the project manager of changes


正确答案:B

第9题:

The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .

A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer

答案:C
解析:
实施整体变更控制过程是从项目开始到项目结束并且是项目经理的最终责任。

第10题:

The perform Integrated Change Contorl process is the uitimste responsbilityof the( ),Although changes my be intitated verbally,y they should be recorded in writtern form and entered into the(请作答此空)syste.

A.quality sanagement
B.configurat ion sanagesent
C.risk Banagement
D.scope management

答案:B
解析:
执行综合变更控制过程是(73)的首要责任,尽管口头上对变更进行了说明,但它们应以书面形式记录并输入(74)系统。(73)A.资源管理员B.部门经理C.职能经理D.项目经理
(74)A.质量管理B.配置管理C.风险管理D.范围管理