Those items are often estimated in terms of resource ( ) , budget and duration.Linked by dependencies and scheduled events.A.finding B.balance C.allocation D.distribution

题目
Those items are often estimated in terms of resource ( ) , budget and duration.Linked by dependencies and scheduled events.

A.finding
B.balance
C.allocation
D.distribution
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A negative cost variance and positive schedule variance means:

A The project is under budget and ahead of schedule

B The project is over budget and behind schedule

C The project is over budget and ahead of schedule

D The project will be overrun but ahead of schedule at completion


正确答案:C

第2题:

72 Project trade-offs vary between

A. risk, cost and schedule.

B. direct cost, indirect cost, and resource availability

C. quality, schedule and time

D. cost, quality and schedule

E. contract terms, scope and budget


正确答案:D

第3题:

Project trade-offs vary between

A . risk, cost and schedule.

B . direct cost, indirect cost, and resource availability

C . quality, schedule and time

D . cost, quality and schedule

E . contract terms, scope and budget


正确答案:D

 

第4题:

● The Work Breakdown Structure (WBS) is the basis for communicating:

A Project scope, cost control, schedule, quality

B Project objectives, dependencies, plan, cost control

C Project scope, schedule, staffing, cost control

D Project scope, quality, schedule, dependencies

E Project budget, schedule, risk factors, work assignments.


正确答案:A

第5题:

The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.

A.estimating

B.defining

C.planning

D.sequencing


参考答案:A

该题的关键词为"schedule activity durations",其语句结构为"The process(主语)of()schedule activity durations uses(谓语)information",语句的含义为"(?)进度活动持续时间的过程使用信息",结合选项,此处应该选择动词,所以观察对进度活动持续时间采取什么行为会应用到各种信息(information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities),只有在估算进度活动持续时间时才会使用这些信息得到活动的工期,其他选项容易排除,因而选项A符合题意要求。

第6题:

114 The Cost Performance Index is computed as:

A. budget cost of work performed divided by actual cost of work performed

B. budget cost of work performed minus actual cost of work performed

C. budget cost of work performed minus budget cost of work scheduled

D. budget cost of work scheduled divided by budget cost of work performed

E. actual cost of work scheduled divided by budget cost of work performed


正确答案:A

第7题:

96 A negative cost variance and positive schedule variance means:

A. The project is under budget and ahead of schedule

B. The project is over budget and behind schedule

C. The project is over budget and ahead of schedule

D. The project will be overrun but ahead of schedule at completion


正确答案:C

第8题:

The Cost Performance Index is computed as:

A . budget cost of work performed divided by actual cost of work performed

B . budget cost of work performed minus actual cost of work performed

C . budget cost of work performed minus budget cost of work scheduled

D . budget cost of work scheduled divided by budget cost of work performed

E . actual cost of work scheduled divided by budget cost of work performed


正确答案:A

第9题:

The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

A.estimating

B.defining

C.planning

D.sequencing


参考答案:D

第10题:

Estimating activity durations uses information on activity scope of(74) , required resource types, estimated resource quantities, and resource calendars.

A.milestone

B.baseline

C.quality

D.work


正确答案:D
解析:估算活动历时使用的信息包括活动的工作范围、所需资源类型、估算的资源数量,以及资源日历。