职称英语(理工)

Employers must consider all candidates impartially and without bias.A:immediately B:correctly C:fairly D:carefully

题目
Employers must consider all candidates impartially and without bias

A:immediately
B:correctly
C:fairly
D:carefully
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

123 The scope of a project can be expected to change if:

A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs

C. The project manager is assigned after the project is defined, and the cost and schedule are approved D. A clear objective is not provided

E. All of the above are possible based upon the situation


正确答案:E

第2题:

Generally speaking, the best time to inquire the result of the job interview is in the end of it when all the candidates have finished their interview.()


参考答案:错
解析:The best time to follow up the interview is two days after.

第3题:

The scope of a project can be expected to change if:

A.The project manager must provide cost estimates without having a design concept

B.Oversimplification (underestimating) of the nature of the work occurs

C.The project manager is assigned after the project is defined, and the cost and schedule are approved

D.A clear objective is not provided

E.All of the above are possible based upon the situation


正确答案:E

第4题:

How could you rearrange all the important things without your ___________ (concentrate)?


参考答案:concertration

第5题:

Parallelism is used in ________.

A、It sells us instant gratification. It diverts us only to divert, to make the time pass without pain.

B、Consider the casual assumptions that television tends to cultivate: that complexity must be avoided, that visual stimulation is a substitute for thought, that verbal precisio is an anachronism.

C、Television’s variety becomes a narcotic, not a stimulus.

D、Everything about this nation – the structure of the society, its forms of family organization, its economy, its place in the world – has become more complex, not less.


参考答案:ABD

第6题:

● The scope of a project can be expected to change if:

A The project manager must provide cost estimates without having a design concept

B Oversimplification (underestimating) of the nature of the work occurs

C The project manager is assigned after the project is defined, and the cost and schedule are approved

D A clear objective is not provided

E All of the above are possible based upon the situation


正确答案:E

第7题:

Department of Credit must consider budgetary target, net revenue and ______.

A.risk

B.cost

C.liquidity

D.others


正确答案:B
解析:budgetary target预算目标。net revenue净收益。liquidity流动性。

第8题:

41 The scope of a project can be expected to change if:

A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occurs

C. The project manager is assigned after the project is defined, and the cost and schedule are approved

D. A clear objective is not provided

E. All of the above are possible based upon the situation


正确答案:E

第9题:

You ( ) me, because I never said I liked coffee without milk.

A、must misunderstand

B、must have misunderstood

C、must be misunderstanding

D、had to misunderstand


参考答案:B

第10题:

Given two different character sets (A and B), which of the following must be true for A to be considered a strict superset of B?()

A. A must contain all of the characters defined in B

B. A must be Unicode

C. The encoded values in A must match the encoded values in B for all characters defined in B

D. A must be a multibyte character set

E. The encoded values in A must match the encoded values in B for all numeric and alphabetic characters in B


参考答案:A, C

更多相关问题