第1题:
A.taken part
B.taken sides
C.taken place
D.taken leave
第2题:
Perhaps the experiment _____ by this time tomorrow.
A、has been done
B、will have been bone
C、will do
D、would have done
第3题:
During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A.Now becomes the new schedule, including the changes, and the original baseline is disregarded.
B.Is still the original baseline but annotated to reflect that a change has taken place.
C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D.Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E.Is the same since baseline schedules cannot change once the development phase is completed.
第4题:
第5题:
第6题:
A. took place
B. had taken place
C. were taken place
D. had been taken place
第7题:
A. took place
B. has taken place
C. has been taken place
D. have taken place
第8题:
156 During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule:
A. Now becomes the new schedule, including the changes, and the original baseline is disregarded. B. Is still the original baseline but annotated to reflect that a change has taken place.
C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
E. Is the same since baseline schedules cannot change once the development phase is completed
第9题:
第10题: