其它

( )The process of translating the quality management plan into eecutable quality activities that incorporate the organization's quality policies into the project.A:Munage quality B:Quality audit C:Quality metrics D:Quality improvement

题目
( )The process of translating the quality management plan into eecutable quality activities that incorporate the organization's quality policies into the project.

A:Munage quality
B:Quality audit
C:Quality metrics
D:Quality improvement
参考答案和解析
答案:C
解析:
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

87 The key ingredient to a successful quality management program are _____.

A. management's quality philosophy, operational quality assurance and operational quality control. B. quality evaluation methods and functional quality integrators.

C. technical quality administration, the technical quality specifications, and the quality process review. D. quality evaluation methods, quality progress reviews and the technical quality specifications.

E. All of the above


正确答案:A

第2题:

Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

A.Project

B.project management team

C.performingorganization

D.customer


参考答案:C

该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

第3题:

The key ingredient to a successful quality management program are _____.

A . management's quality philosophy, operational quality assurance and operational quality control.

B . quality evaluation methods and functional quality integrators.

C . technical quality administration, the technical quality specifications, and the quality process review.

D . quality evaluation methods, quality progress reviews and the technical quality specifications.

E . All of the above.


正确答案:A

第4题:

Perform. Quality Control is the process of monitoring and recording resuks of executing the Quality Plan activities to assess performance and recommend necessary changes.( )are the techniques and tools in performing quality control. ①Activity network diagram②Cause and effect diagrams③Inspection④Flow chart⑤Work Breakdown Structure⑥Pareto chart A.①③⑤ B.②④⑤⑥ C.②③④⑤⑥ D.①②③④⑥


正确答案:D
执行质量控制是一个监督、评价项目质量计划活动执行结果和提出变更请求的过程。执行质量控制的技术和工具包括:活动网络图(Activity network diagram)、因果图(Cause and effect diagrams)、检查(Inspection)、流程图(Flow chart)和帕累托图(Pareto chart)等,但不包括工作分解结构(Work Breakdown Structure)。

第5题:

The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.

A.Manage quality

B.Quality audit

C.Quality metrics

D.Quality improvement


正确答案:A

第6题:

Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

A.Benchmarking

B.Quality metric

C.Quality checklist

D.Brainstornung


参考答案:A

第7题:

● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

A.performance

B.process

C.product

D.object


正确答案:C

第8题:

● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.

(71)

A. project

B. project management team

C. performing organization

D. customer


正确答案:C

第9题:

●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.

(71)A. Benchmarking

B. Quality metric

C. Quality checklist

D. Brainstorming


正确答案:A

第10题:

Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object


正确答案:C

项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

更多相关问题