ompany.com has recently received a new p5-570 in the data center and wants to connect it to an existing HMC environment where each of the existing POWER5 servers has been assigned a static IP address. Which of the following actions should the technical specialist perform to set the service processor network address for a static IP?()
第1题:
An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
第2题:
An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC. Which infrastructure is required for the new HMC?()
第3题:
An administrator has an existing HMC and POWER6 570 connected to a network switch. The administrator is planning to install two POWER6 570s with a dedicated HMC.Which infrastructure is required for the new HMC?()
A.An additional switch for the new HMC
B.Asynchronous adapters on the new HMC
C.The two 570 servers are directly connected to the new HMC
D.One 570 is directly connected to the new HMC and the other is directly connected to the existing HMC
第4题:
A new array of hard drives has been added to an existing server; however, when the server is booted into the Windows OS the new drives fail to appear in My Computer. From which of the following locations can the new storage drives be added?()
第5题:
our company has four DNS servers that run windows 2008. Each server has a static ip address. You need to prevent dhcp from assigning the addresses of the DNS servers to DHCP clients. What should you do?()
第6题:
Company.com has recently received a new p5-570 in the data center and intends to Micro-Partition the server. In which order should installation steps be taken?()
第7题:
A medical customer has a rack with four BladeCenter H chassis that have been operating normally for several months. After installing a new rack of servers in the data center, the system administrator notices the blowers in the BladeCenters have increased their speed. Which of the following caused this problem? ()
第8题:
A customer has an existing high availability SAN environment with CLARiiON, which has been stable for 16 months. They have recently experienced several outages with their current storage systems. They need to purchase additional storage and have asked about tier 1 storage. They are concerned with connecting their existing storage and servers without trouble.Which resource should be consulted while developing the solution options?()
A. Disk Magic
B. TPC for Data
C. CLARiiON Procedure Generator
D. System Storage Interoperability Center
第9题:
The current data center has run out of space. A room that is located next to the existing data center is then used to house two racks containing six servers. Six months later, physical housekeeping is performed as part of a mid-year maintenance plan. Which environmental condition discovered in the room is LEAST critical?()
第10题:
Companycom has several CR3 HMCs managing their p690 servers. They have purchased a new p5 570 and would like to manage the new system with an existing HMC. What is required to support this environment?()