A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single H

题目

A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()

  • A、Purchase a second HMC and use this to manage the new servers.
  • B、Connect all of the new servers to the existing private HMC network.
  • C、Configure a second private network on their existing HMC for the new servers.
  • D、Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th.
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The systems administrator of a large manufacturer has POWER5 and POWER6 servers, each with LPARs running AIX 6.1.  They are running several workloads including SAP, DNS, Oracle, DB2 and WebSphere Application Server, and plan to consolidate onto one POWER7 server.   How can the system administrator determine how much benefit Active Memory Expansion (AME) could provide for the consolidated system?()

  • A、Run amepat now on all of the existing LPARs.
  • B、Run amepat after consolidation on all LPARs.
  • C、Run amepat now on all existing LPARs running on the POWER6 servers.
  • D、Run amepat now on all existing LPARs running database applications.

正确答案:A

第2题:

A customer has an IBM System Storage Enterprise Storage Server and several EMC CX3 systems installed in a data center, attached to IBM System p servers. As a step toward data consolidation, they intend to put all data on a new DS8700.  What would be the most important data migration factors to consider()

  • A、sector size and the amount of production data
  • B、existing RAID levels and the disk drive speed
  • C、sector size and existing RAID levels
  • D、amount of production data and the disk drive speed

正确答案:D

第3题:

When ordering a new IBM Power Systems server, a customer is given the option of two types of Hardware Management Console:7042-CR4 and 7042-C06.Which main difference between the options would influence the customer‘s decision?()

A.The 7042-CR4 is a rack mounted model, compared to the 7042-C06, which is adesktop.

B.The 7042-CR4 is limited to 16 managed systems, compared to a limit of 32 for the 7042-C06.

C.The 7042-C06 has faster CPUs and twice the RAM compared to the 7042-CR4,which is suited to large enterprise deployments.

D.The 7042-C06 can manage POWER5-based hardware, in addition to POWER6, while the 7042-CR4 can only manage POWER6-based hardware.


参考答案:C

第4题:

A customer wants to run VMWare ESX on an x445 with a large number of virtual machines running Windows 2003 Server as a Disaster Recovery (DR) Site for the production environment.  Which of the following questions would most impact the memory configuration?()

  • A、What version of VMWare ESX Server is being considered?
  • B、Do the systems currently use Double Data Rate (DDR) memory?
  • C、What is the total number of processors installed in the production systems?
  • D、What is the total amount of memory currently being used across all the production systems?

正确答案:D

第5题:

A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()

  • A、 Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.
  • B、 Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.
  • C、 Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.
  • D、 Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

正确答案:D

第6题:

A customer has ten RS/6000 Model M80, two pSeries 690 Model 681, five POWER5 510 and two POWER6 560 machines installed and running commercial applications. They want to do a server consolidation study in order to replace the existing systems with POWER7 systems. What performance metric is recommended when evaluating the replacement system?()

  • A、IBM CPW
  • B、IBM rPerf
  • C、SPECint_rate2006
  • D、IDEAS International RPE2

正确答案:B

第7题:

A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored? ()

  • A、 Identify which systems are the most critical and bring them up by level of importance.
  • B、 Retrieve the latest backup tapes for immediate system restore using the GFS rotation.
  • C、 Identify the least critical systems and then power those systems on first.
  • D、 Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.

正确答案:A

第8题:

A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server.  What is the minimum PowerVM edition that supports the customer requirement?()

  • A、 PowerVM Lx86
  • B、 PowerVM Express Edition
  • C、 PowerVM Standard Edition
  • D、 PowerVM Enterprise Edition

正确答案:C

第9题:

A customer has a combination of fifteen Windows file servers with direct attached storage and three Power Systems with AIX database servers SAN attached to a DS4700.  They would like to upgrade and plan for 40 TB capacity.  The customer needs to move to a more scalable storage system to include all servers.Which of the following would be most appropriate to ask first?()

  • A、What are the plans for Disaster Recovery? 
  • B、What are the plans for data migration? 
  • C、Would iSCSI meet your needs? 
  • D、How much space is available in the current storage systems?

正确答案:B

第10题:

A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()

  • A、Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs
  • B、Move the existing physical network and storage adapters to the new system and virtualize the I/O using a  single VIO Server.
  • C、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC  connectors and dual HBAs.
  • D、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC  connectors and the other with dual HBAs.

正确答案:C