CompTIA认证考试

Scheduled preventative maintenance visits should be carried out:()A、after two unplanned service calls.B、according to manufacturers specifications.C、when the device is becoming unreliable.D、every sixty days.

题目

Scheduled preventative maintenance visits should be carried out:()

  • A、after two unplanned service calls.
  • B、according to manufacturers specifications.
  • C、when the device is becoming unreliable.
  • D、every sixty days.
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

114 The Cost Performance Index is computed as:

A. budget cost of work performed divided by actual cost of work performed

B. budget cost of work performed minus actual cost of work performed

C. budget cost of work performed minus budget cost of work scheduled

D. budget cost of work scheduled divided by budget cost of work performed

E. actual cost of work scheduled divided by budget cost of work performed


正确答案:A

第2题:

After circling around the earth for three days, Shenzhou Spaceship received the command from the ground that _____(它着陆)as scheduled the next day. (land)


正确答案:
79. it (should) land

第3题:

You have summarized the project and note that , hours have been scheduled, , hours have been earned and , hours paid. The correct conclusion is:

A.The project is operating at a favorable cost efficiency ratio.

B.the project is spending more than planned

C.the project is behind schedule

D.the project is ahead of schedule

E.B and C


正确答案:C
C

第4题:

A series of debates between lectures _____ scheduled for next weekend.

A、were

B、was

C、are

D、be


参考答案:B

第5题:

This year is the year of mouse in the lunar().

A、time

B、calendar

C、schedule

D、timetable


参考答案:B

第6题:

39 You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:

A. The project is operating at a favorable cost efficiency ratio.

B. the project is spending more than planned

C. the project is behind schedule

D. the project is ahead of schedule

E. B and C


正确答案:C

第7题:

A __of the long report by the budget committee was submitted to the mayor for approval.

A.shorhand

B.scheme

C.schedule

D.sketch


正确答案: D

第8题:

The Cost Performance Index is computed as:

A . budget cost of work performed divided by actual cost of work performed

B . budget cost of work performed minus actual cost of work performed

C . budget cost of work performed minus budget cost of work scheduled

D . budget cost of work scheduled divided by budget cost of work performed

E . actual cost of work scheduled divided by budget cost of work performed


正确答案:A

第9题:

The plane is scheduled to () at 4 o'clock.

A、take up

B、take off

C、take on

D、take out


参考答案:B

第10题:

An operator wants to view all the scheduled jobs on a system. Which of the following locations would house scheduled jobs?()

A. /etc/var/spool

B. /var/spool/cron

C. /var/sched/jobs

D. /usr/sched/crontabs


参考答案:C

更多相关问题