CompTIA认证考试

Acceptance of deliverables to multiple locations requires which type of sign off?()A、Design AcceptanceB、Code AcceptanceC、Module AcceptanceD、Site Acceptance

题目

Acceptance of deliverables to multiple locations requires which type of sign off?()

  • A、Design Acceptance
  • B、Code Acceptance
  • C、Module Acceptance
  • D、Site Acceptance
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

A.Project acceptance

B.Scope verification

C.Scope definition

D.WBS Creation


正确答案:B
解析:范围验证是指获取项目干系人对已完成的项目范围的正式认可的过程。验证范围包括了评审可交付物和工作成果,以确定它们均已令人满意地完成。

第2题:

()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。

A、Validate scope

B、Define scope

C、Control scope

D、Collect requirement


正确答案:C

第3题:

In acceptance sampling, if the sample size is kept the same but the acceptance number is increased, which of the following will be true:

A . buyer's risk will decrease

B . vendor's risk will decrease

C . producer's risk will decrease

D . consumer's risk will increase

E . C and D only


正确答案:E

第4题:

() is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily.

A.Project acceptance
B.Scope verification
C.Scope definition
D.WBS Creation

答案:B
解析:
范围验证是指获得项目干系人对已完成的项目范围的正式认可的过程。验证范围包括了评审可交付物和工作成果,以确定它们均已令人满意地完成。

第5题:

( )must be between on-line deployment and final acceptance.

A.Detailed design B.Test runC.Internal testing D.Contract signing


正确答案:B

第6题:

听力原文:A cheque is never accepted by the bank on which it is drawn. Hence, the rules relating to acceptance of bills do not apply to cheques.

(9)

A.A cheque can be accepted by the bank on which it is drawn.

B.A bill can not be accepted by the bank on which it is drawn.

C.The rules relating to acceptance of bills are not applicable to cheques.

D.The rules relating to acceptance of bills are applicable to cheques.


正确答案:C
解析:单句意思为“支票绝不会由作为受票人的银行来承兑,因此,有关汇票承兑的原则不适用于支票”。

第7题:

the () is primarily concerned with acceptance of the deliverables.while quality control is primarily concerned with correctness of the deliverables and meeting the quality requirements specified for the deliverables

A.verify scope

B.define scope

C.quality assurance

D.validate scope


正确答案:A
解析:()是接受可交付成果主要考虑的因素。质量控制主要考虑可交付成果的正确性,并关注可交付物符合质量需求的程度A、确认范围B、定义范围C、质量保证D、验证范围

第8题:

is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

A.WBS Creation

B.Scope definition

C.Project acceptance

D.Scope verification


正确答案:D

第9题:

As each application module is completed, it undergoes ()to ensure that it operates correctly and reliably.

A.unit testing
B.integration testing
C.system testing
D.acceptance testing

答案:A
解析:
本题考察计算机专业知识当每个应用程序模块完成后,它将执行(),以确保其正确、可靠地运行A 单元测试B 集成测试C 系统测试D 验收测试

第10题:

The()process differs from the()process in that the former is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with correctness of the deliverables.

A.perform Quality Assurance
B.Validate Scope
C.Control Quality
D.Define Scope

答案:C
解析:
本题翻译:
验证的范围过程不同于()过程,前者主要关注可交付成果的接受,而后者主要关注可交付成果的正确性。
A.执行质量保证
B.验证的范围
C.质量控制
D.定义范围

更多相关问题