国际货运代理

The general additional risks including()are covered in all risks coverage.A、risk of shortageB、risk of leakageC、strikes riskD、risk of rust

题目

The general additional risks including()are covered in all risks coverage.

  • A、risk of shortage
  • B、risk of leakage
  • C、strikes risk
  • D、risk of rust
参考答案和解析
正确答案:A,B,D
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

15 Total project risk can be defined as:

A. the sum of the probabilities of project risks events times the sum of consequences of those risks

B. the sum of the products of each project risk event times its consequences

C. the sum of the consequences of all project risk events

D. the sum of the probabilities of all project risk events

E. 1 - the sum of the probabilities of all project risk events


正确答案:B

第2题:

The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


正确答案:A
风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

第3题:

Project Risk Management is based on which of the following premises:

A the future is unknown.

B unknowns can result in risks or opportunities.

C we cannot control risk events.

D project risk impact can be measured and controlled

E All of the above.


正确答案:E

第4题:

Since risk is associated with most projects,the best course of action is to (71)

A.cover all project risks by buying appropriate insurance

B.ignore the risks,since nothing can be done about them and move forward with the project in an expeditious manner

C.avoid project with clear and present risk

D.identify various risks and implement actions to mitigate their potential impact


正确答案:D
识别所有风险,潜在应对措施。

第5题:

●Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the (73).

(73)A. project management plan

B. project baseline

C. risk response plan

D. risk baseline


正确答案:A

第6题:

108 Project Risk Management is based on which of the following premises:

A. the future is unknown.

B. unknowns can result in risks or opportunities.

C. we cannot control risk events.

D. project risk impact can be measured and controlled

E. All of the above


正确答案:E

第7题:

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.()A.Risk Identification B.Quantitative Risk AnalysisC.Qualitative Risk Analysis D.Risk Monitoring and Control


正确答案:B
定量风险分析过程分析风险事件的影响并对这些影响赋予一个数值化的评价。

第8题:

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.


正确答案:B

第9题:

Banks in international lending face the risks common to all banks: liquidity risk, interest rate risk, credit (asset) risk, and contingent liabilities risk.

A.Right

B.Wrong

C.Doesn't say


正确答案:C
解析:文章通篇提及银行面临的三类风险,并加以举例,并没有提及Banks in international lending。

第10题:

Setting redundant components in subsystem to handle with the risks brought by the defaults of original components, what kind of risk response strategy is this ? ( 75 ).

A.Risk avoidance

B.Risk acceptance

C.Risk mitigation

D.Contingency plan


正确答案:C

更多相关问题