软件水平考试

()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.A.identify risks B.monitor risks C.implement risks responses D.plan risk management

题目
()is the process of identifying individual project risks as well as source of overall project risk,and documenting their characteristics.

A.identify risks
B.monitor risks
C.implement risks responses
D.plan risk management
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Risk management allows the project manager and the project team to:

A eliminate most risks during the planning phase of the project

B identify project risks

C identify impacts of various risks

D plan suitable responses

E B, C and D only


正确答案:E

第2题:

122 Total Project Risk:

A. should not be calculated for small projects

B. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D. A and B

E. A and C


正确答案:C

第3题:

Total Project Risk:

A should not be calculated for small projects

B is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.

C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.

D A and B

E A and C


正确答案:C

第4题:

Risk management allows the project manager and the project team not to(71). A.eliminate most risks during the planning phase of the project B.identify project risks C.identify impacts of various risks D.plan suitable responses


正确答案:A
风险管理并不能使得项目经理及其团队在项目的规划过程中避免大多数的风险。

第5题:

●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.

(71)

A. Quantitative Risk Analysis

B. Qualitative Risk Analysis

C. Enterprise Environmental Factors

D. Risk Management Plan


正确答案:B

第6题:

15 Total project risk can be defined as:

A. the sum of the probabilities of project risks events times the sum of consequences of those risks

B. the sum of the products of each project risk event times its consequences

C. the sum of the consequences of all project risk events

D. the sum of the probabilities of all project risk events

E. 1 - the sum of the probabilities of all project risk events


正确答案:B

第7题:

Define Activities is the process of identifying the specific actions to be performed to produce the (71).

A.project elements

B.work drafts

C.work package

D.project deliverables


正确答案:D
解析:活动定义过程识别是为了生产项目的可交付物而必须执行的具体活动。

第8题:

Total project risk can be defined as:

A the sum of the probabilities of project risks events times the sum of consequences of those risks

B the sum of the products of each project risk event times its consequences

C the sum of the consequences of all project risk events

D the sum of the probabilities of all project risk events

E 1 - the sum of the probabilities of all project risk events.


正确答案:B

第9题:

______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.

A.Quantitative Risk Analysis

B.Qualitative Risk Analysis

C.Enterprise Environmental Factors

D.Risk Management Plan


正确答案:B
解析:定性风险分析利用风险发生概率、风险一旦发生对项目产生的影响以及其他因素(如时间框架和项目制约条件,即成本、进度、范围、质量的风险承受度水平),对已识别风险进行优先级的评估。
选项A是定量风险分析,选项B是定性风险分析,选项C是企业环境因素,选项D是风险管理计划。故B是正确的。

第10题:

The( )process ascertains which risks have the potential of affecting the project and documenting the risks’characteristics. A.Risk Identification B.Quantitative Risk Analysis C.Qualitative Risk Analysis D.Risk Monitoring and Control


正确答案:A
风险识别(RiskIdentification)是确定何种风险可能会对项目产生影响,并将这些风险的特征形成文档。

更多相关问题