CMS专题

单选题Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.A IntegrationB TimeC PlanningD Commun

题目
单选题
Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.
A

Integration

B

Time

C

Planning

D

Communication

参考答案和解析
正确答案: D
解析: 该题的关键词较多,不过都是并列的关系,包括"ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition、 projectinformation"。其主要语句结构为"Project()Management(主语)is(谓语)the Knowledge Area",含义为"项目什么管理是知识领域",后续的定语从句说明该知识领域的特点。其实根据关键词"Proj ect information"考生可以很容易识别出来应该是项目沟通管理。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

● Scope management is:

A a project control function.

B employs change control.

C a work authorization process.

D considers Cost, Quality and Schedule.

E All of the above.


正确答案:E

第2题:

● The inputs of developing project management plan do not include (72).

(72)

A. project charter

B. stakeholder management strategy

C. project scope statement

D. outputs from planning processes


正确答案:B

第3题:

● Project (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

A.Integration

B.Time

C.Planning

D.Communication


正确答案:D

第4题:

The inputs of developing project management plan do not include(72). A.project charter B.stakeholder management strategy C.project scope statement D.outputs from planning processes


正确答案:B
制定项目管理计划的输入不包括干系人管理策略(stakeholder management strategy)。

第5题:

The inputs of developing project management plan do not include (72) .

A.project charter

B.stakeholder management strategy

C.project scope statement

D.outputs from planning processes


正确答案:B

第6题:

● Project Quality Management must address the management of the projecand the (72) of the project. While Project Quality Management applies to alprojects, regardless of the nature of their product, product quality measureand techniques are specific to the particular type of product produced by thproject.

A.performance

B.process

C.product

D.object


正确答案:C

第7题:

● The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)

(75)

A. Project Scope Statement

B. Project Management Plan

C. Forecasts

D. Project Charter


正确答案:B

试题(75)分析
  项目管理的过程开发计划,包括采取必要的定义,准备,集成和协调所有组成计划到    (75) 。
  A.项目范围说明书                    B.项目管理计划
  C.项目预测                          D.项目章程
参考答案
  (75)B

第8题:

Scope management is:

A.a project control function.

B.employs change control.

C.a work authorization process.

D.considers Cost, Quality and Schedule.

E.All of the above.


正确答案:E
E

第9题:

The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter


正确答案:B
制定项目管理计划过程定义、准备、集成和协调所有的分计划,以形成项目管理计划 。

第10题:

Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning D.Communication


正确答案:D
项目沟通管理是使用所需过程以确保及时、恰当地产生、收集、分发、存储、收回和最终处置项目信息的知识域。