CMS专题

单选题The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.A subdividingB assessingC planningD integrating

题目
单选题
The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.
A

subdividing

B

assessing

C

planning

D

integrating

参考答案和解析
正确答案: B
解析: 该题的关键词为"work breakdown structure、 major project deliverables",其语句结构为"The creation ofa work breakdown structure (WBS)(主语)is(谓语)the processof()the major project deliverables",含义为"创建WBS是怎样主要的项目交付物的过程"。根据WBS定义以及选项,容易识别出应选择分解(subdividing)
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?

A.Time, schedule and cost.

B.Management coordination and organization structuring.

C.Work methods and accountability.

D.Quality of work.

E.Risk and impact decision-making.


正确答案:D
D

第2题:

106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:

A. Work packages.

B. Subtasks.

C. Tasks.

D. Code of accounts.

E. Integration points


正确答案:C

第3题:

The work breakdown structure (WBS) is first developed in which scope management process?

A . Initiation

B . Scope planning

C . Scope change control

D . Scope Definition

E . Scope verification


正确答案:D

 

第4题:

● A work breakdown structure is most useful for:

A identifying individual tasks for a project

B scheduling the start of tasks

C developing a cost estimate

D determining potential delays

E A and C


正确答案:E

第5题:

23 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation

B. Scope planning

C. Scope change control

D. Scope

Definition

E. Scope verification


正确答案:D

第6题:

The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:

A.Work packages.

B.Subtasks.

C.Tasks.

D.Code of accounts.

E.Integration points.


正确答案:C

C

第7题:

141 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation

B. Scope planning

C. Scope change control

D. Scope Definition

E. Scope verification


正确答案:D

第8题:

The Work Breakdown Structure (WBS) is the basis for communicating:

A.Project scope, cost control, schedule, quality

B.Project objectives, dependencies, plan, cost control

C.Project scope, schedule, staffing, cost control

D.Project scope, quality, schedule, dependencies

E.Project budget, schedule, risk factors, work assignments.


正确答案:A
A

第9题:

● When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the

A task

B level of effort

C sub-task

D project

E work package


正确答案:E

第10题:

● A Work Breakdown Structure:

A assures all work is identified

B subdivides the project into manageable segments

C provides the project sponsor with a time-phase task summary

D both A and B

E All of the above.


正确答案:D

更多相关问题