信息系统项目管理师

单选题()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.These other projects can be within the performing organization or outside of it

题目
单选题
()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.These other projects can be within the performing organization or outside of it,and can be within the same or in another application area.
A

Metrics

B

Measurement

C

Benchmarking

D

Baseline

参考答案和解析
正确答案: D
解析: 该题的关键词为"comparing actual or planned project practices to those of other proj ects",其语句结构为"()(主语)involves(谓语)comparing actual or planned project practices to those of other projects",含义为"什么涉及到将实际或计划的项目实践同其他项目实践比较",比较项目实践是质量管理方法比较基准(Benchmarking)的主要特征。因而选择选项C。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

A Significantly reduce project risks

B eliminate project risks

C provide a rational basis for better decision making

D identify risks, their impact(s), and any appropriate responses

E None of the above.


正确答案:B

第2题:

Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

A.Benchmarking

B.Quality metric

C.Quality checklist

D.Brainstornung


参考答案:A

第3题:

Bar charts are most appropriate for:

A.Comparing actual to planned performance to each activity.

B.Showing slack time.

C.Showing critical path dependencies.

D.Showing which activities can be rearranged in parallel.

E.All of the above.


正确答案:A
A

第4题:

involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it,and can be within the same or in another application area.

A.Metrics

B.Measurement

C.Benchmarking

D.Baseline


正确答案:C
解析:基准分析涉及到将实际或计划的项目实践与其他项目进行比较,以产生改进的思想并提供一个测量绩效的基准。其他项目可以是执行组织内部的,也可以是外部的,可以是同一个应用领域的,也可以是其他应用领域的。

第5题:

● Bar charts are most appropriate for:

A Comparing actual to planned performance to each activity.

B Showing slack time.

C Showing critical path dependencies.

D Showing which activities can be rearranged in parallel.

E All of the above.


正确答案:A

第6题:

178 "Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .

A. be completed in reduced overall time than other projects.

B. be in a higher risk category than other projects.

C. not be compatible with project risk and assessment

D. A and B

E. All of the above


正确答案:D

第7题:

In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

A.Strongmatrix

B.Projectized

C.Projectcoordinator

D.Weakmatrix


参考答案:B

第8题:

"Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .

A be completed in reduced overall time than other projects.

B be in a higher risk category than other projects.

C not be compatible with project risk and assessment

D A and B

E All of the above.


正确答案:D

第9题:

● Which of the following statement related to PMO is not correct? (71)

(71)

A. The specific form, function, and structure of a PMO is dependent upon the needs of the organization that it supports.

B. One of the key features of a PMO is managing shared resources across all projects administered by the PMO.

C. The PMO focuses on the specified project objectives.

D. The PMO optimizes the use of shared organizational resources across all projects.


正确答案:C

第10题:

●Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools, which involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance.

(71)A. Benchmarking

B. Quality metric

C. Quality checklist

D. Brainstorming


正确答案:A