单选题A Power 720 has AIX 6.1 and Linux partitions.During normal workloads there is more than enough memory available to the LPARs.  During month-end processing one partition becomes memory constrained.      What can help overcome this situation?()A Active M

题目
单选题
A Power 720 has AIX 6.1 and Linux partitions.During normal workloads there is more than enough memory available to the LPARs.  During month-end processing one partition becomes memory constrained.      What can help overcome this situation?()
A

Active Memory Sharing (AMS)

B

Active Memory Expansion (AME)

C

Integrated Virtual Memory (IVM)

D

Memory Capacity on Demand (CoD)

如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A system administrator is creating four LPARs on a Power 550. The Power 550 has 64GB of memoryinstalled and 32GB activated. The system administrator sets the minimum dedicated memory to 8GB in the profile for each LPAR. After activating three LPARs, he is not able to activate the fourth LPAR. What is the likely cause of the problem?()

  • A、The Power 550 is licensed for three LPARs only.
  • B、There is not enough memory to meet the minimum dedicated memory requirement for the fourth LPAR. A faulty memory DIMM is detected in the POWER5 550.
  • C、There is not enough memory to meet the minimum dedicated memory requirement for the fourth LPAR. The HMC reserves some memory to perform logical partition tasks.
  • D、There is not enough memory to meet the minimum dedicated memory requirement for the fourth LPAR. The hypervisor reserves some memory to perform logical partition tasks.

正确答案:D

第2题:

A small IT department is deploying Power 720 servers exploiting virtualization technologies.  Each Power 720 will have two partitions, one with 6 cores and one with 2 cores, and both partitions having 32GB of memory each. Live Partition Mobility is being considered at some point in the future. What is the minimum AIX Edition required to support the customer?()

  • A、AIX Basic Edition
  • B、AIX Express Edition
  • C、AIX Standard Edition
  • D、AIX Enterprise Edition

正确答案:C

第3题:

●OS can use (72) memory to run processes that require more main memory than is actually available.

(72)

A. virtual

B.imaginary

C.abstract

D.false


正确答案:A

第4题:

Micro-Partitioning can be defined as().

  • A、multiple partitions that share the processing power of a set of physical processors where a partition can be assigned as little as 1/2 of a physical processor's resource. 
  • B、multiple partitions that share the processing power of a set of physical processors where a partition can be assigned as little as 1/100th of a physical processor's resource. 
  • C、an advanced virtualization feature of POWER5 systems with Linux (SUSE and Red Hat for POWER) and AIX 5L Version 5.3 that allows multiple partitions to share the processing power of a set of physical processors. 
  • D、an advanced virtualization feature of POWER5 systems with Linux (SUSE and Red Hat for POWER) and AIX 5L Version 5.2 or 5.3 that allows multiple partitions to share the processing power of a set of physical processors.

正确答案:C

第5题:

A customer has a Power 770 running an SAP ERP workload on AIX 7. It has a single partition with 12 cores and 48GB of memory and the CPU is underutilized at 46% with 1000 users. Memory utilization is at 80%. The number of users will increase to 1700, increasing memory utilization by 37%. Which of the following supports this requirement?()

  • A、Active Memory Server
  • B、Active Memory Sharing
  • C、Active Memory Pooling
  • D、Active Memory Expansion

正确答案:D

第6题:

What operating system is required to support Active Memory Expansion?()

  • A、AIX 6.1
  • B、AIX 5.3
  • C、Red Hat 10
  • D、SUSE LINUX 11

正确答案:A

第7题:

After purchasing the Active Memory Expansion (AME) Enablement Feature,what tasks must be completed before AME can be used?()

  • A、Enable using active partition properties with DLPAR
  • B、Enter the activation key via the AIX 6.1 command line and reboot AIX
  • C、Enter the activation key via the HMC,power cycle the managed system and start the LPAR
  • D、Enter the activation key via the HMC,modify the partition profile and restart the LPAR

正确答案:B

第8题:

The systems administrator of a large manufacturer has POWER5 and POWER6 servers, each with LPARs running AIX 6.1.  They are running several workloads including SAP, DNS, Oracle, DB2 and WebSphere Application Server, and plan to consolidate onto one POWER7 server.   How can the system administrator determine how much benefit Active Memory Expansion (AME) could provide for the consolidated system?()

  • A、Run amepat now on all of the existing LPARs.
  • B、Run amepat after consolidation on all LPARs.
  • C、Run amepat now on all existing LPARs running on the POWER6 servers.
  • D、Run amepat now on all existing LPARs running database applications.

正确答案:A

第9题:

A Power 720 has AIX 6.1 and Linux partitions.During normal workloads there is more than enough memory available to the LPARs.  During month-end processing one partition becomes memory constrained.      What can help overcome this situation?()

  • A、Active Memory Sharing (AMS)
  • B、Active Memory Expansion (AME)
  • C、Integrated Virtual Memory (IVM)
  • D、Memory Capacity on Demand (CoD)

正确答案:A

第10题:

Which of the following uses compression/decompression to increase the memory available for client workloads?()

  • A、PowerVM
  • B、VMControl
  • C、Active Memory Sharing
  • D、Active Memory Expansion

正确答案:D