Establishing a project management timetable involves listing milestones,activities,and( )with intended start and finish dates,of which the scheduling of employees may be an element. A.relationships B.resourcesC.stakeholders D.deliverables

题目
Establishing a project management timetable involves listing milestones,activities,and( )with intended start and finish dates,of which the scheduling of employees may be an element.

A.relationships
B.resources
C.stakeholders
D.deliverables
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.

A.Project

B.project management team

C.performingorganization

D.customer


参考答案:C

该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。

第2题:

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.

A.analyze

B.track

C.level

D.extend


正确答案:B
解析:通常,制订项目进度计划是一个反复迭代的过程,该过程确定每个活动和每个里程碑的开工日期和完成日期。制订进度过程要求对历时估算和资源估算进行评审和修订,从而产生一个经过认可的项目进度表,作为对项目进展进行追踪的基准。

第3题:

Free float is the amount of time that an activity may be delayed with out affecting the _____.

A.Early start of the succeeding activities.

B.Late start of the succeeding activities.

C.Project finish.

D.Cost of the project.

E.None of the above.


正确答案:A
A

第4题:

A__(74)__is a type of bar chart that illustrates a project schedul

A.It illustrates the start and finish dates of the terminal elements and summary elements of a project.

B.Gantt chart

C.project histogram

D.milestone chart

E.project flowchart


正确答案:A
甘特图是一种用来描述项目计划的条形图,它描述了项目的各个底层工作单元以及概括性工作单元的开始日期与结束日期。

第5题:

A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.

A.gantt chart

B.project histogram

C.milestone chart

D.project flowchart


正确答案:A

第6题:

● Free float is the amount of time that an activity may be delayed with out affecting the _____.

A Early start of the succeeding activities.

B Late start of the succeeding activities.

C Project finish.

D Cost of the project.

E None of the above.


正确答案:A

第7题:

●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.

(75)

A. analyze

B. track

C. level

D. extend


正确答案:B

第8题:

Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

A.Benchmarking

B.Quality metric

C.Quality checklist

D.Brainstornung


参考答案:A

第9题:

In project management,a ( ) is a list of a project’s milestones,activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.

A.schedule

B.WBS

C.SOW

D.charter


正确答案:A
在项目管理中,进度管理的里程碑清单、活动和可交付物,通常都有明确的开始和结束日期,这些条目通常在资源分配中已经进行估算,在预算和持续时间上依赖于事件的调度。

第10题:

Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an element

A.relationships

B.resources

C.stakeholders

D.deliverables


正确答案:D
解析:建立项目管理的时间表需要里程碑列表、各活动、以及含有估计开始和结束时间的(),其中员工的调度被看作为元素。A,关系B,资源C,干系人D,可交付物