第1题:
● Which of the following is indicative of negative float?
A The late start date is earlier than the early start date.
B The critical path supports the imposed end date.
C The early finish date is equal to the late finish date.
D When leads are employed in the schedule.
E The project is sinking.
第2题:
Define Activities is the process of identifying the specific actions to be performed to produce the (71).
A.project elements
B.work drafts
C.work package
D.project deliverables
第3题:
Which of the following is indicative of negative float?
A.The late start date is earlier than the early start date.
B.The critical path supports the imposed end date.
C.The early finish date is equal to the late finish date.
D.When leads are employed in the schedule.
E.The project is sinking.
第4题:
●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.
(75)
A. analyze
B. track
C. level
D. extend
第5题:
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.
A.analyze
B.track
C.level
D.extend
第6题:
● Free float is the amount of time that an activity may be delayed with out affecting the _____.
A Early start of the succeeding activities.
B Late start of the succeeding activities.
C Project finish.
D Cost of the project.
E None of the above.
第7题:
Project work packages are typically decomposed into smaller components called activities to provide a basis for (72) ,scheduling, executing, and monitoring and controlling the project work.
A.reviewing
B.estimating
C.auditing
D.expecting
第8题:
Free float is the amount of time that an activity may be delayed with out affecting the _____.
A.Early start of the succeeding activities.
B.Late start of the succeeding activities.
C.Project finish.
D.Cost of the project.
E.None of the above.
第9题:
● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).
(71)
A. project elements
B. work drafts
C. work package
D. project deliverables
第10题:
●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.
(74) A. Product scope description
B. Project objectives
C. Product specification
D. The project scope statement