Requirements management is the process of (73) ,analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. A.communicatingB.collectingC.filingD.documenting

题目
Requirements management is the process of (73) ,analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders.

A.communicating
B.collecting
C.filing
D.documenting
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out


正确答案:B
执行(Executing)过程组由为达成项目要求而在项目管理计划中定义的工作的过程组成。

第2题:

The purpose of the requirements definition phase is to produce a clear, complete, consistent, and testable(71 )of the technical requirements for the software product.During the requirements definition phase, the requirements definition team uses an iterative process to expand a broad statement of the system requirements into a complete and detailed specification of each function that the sofrware must perform. and each(72)that it must meet. The starting point is usually a set of high-level requirements from the(73)that describe the project or problem.In either case, the requirements definition team formulates an overall concept for the system and then defines(74)showing how the system will be operated, publishes the system and operations concept document, and conducts a system concept review(SCR).Following the SCR, the team derives(75)requirements for the system from the high level requirements and the system and operations concept. Using structured or object-oriented analysis, the team specifies the software functions and algorithms needed to satisfy each detailed requirement.

A.function

B.definition

C.specification

D.statement


正确答案:C
解析:需求定义阶段的作用就是为软件产品产生一个清晰的、完整的、一致的、可测试的技术需求规格说明。在需求定义阶段,需求定义团队通过迭代过程把有关节系统需求的宽泛的陈述扩展成系列化统必须实现的各个功能的、完整而详细的规格说明,以及系列化统应该满足的各种准则。这个过程的起点通常是由用户提供的描述项目或问题的一组高级需求。在任何情况下,需求定义团队应该阐明与系统有关的整体概念,并且设定一种能够显示系统如何运作的情景,发布有关系统和运行的概念文档,并进行系统概念的评审(SCR)。在SCR之后,团队应该根据高级需求和系统运行概念导出详细的系统需求。通过结构化的或面向对象的分析技术,团队可以规范系统功能,说明满足每一细节需求的算法。

第3题:

● The project maintains a current and approved set of requirements ovethe life of the project by doing the following:

· (73) all changes to the requirements

· Maintaining the relationships among the requirements, the project plansand the work products

· ……

(73)

A. Monitoring

B. Managing

C. Gathering

D. Reducin


正确答案:B

第4题:

Requirements management is the process of (1),analyzing,tracing,prioritizing andagreeing on requirements and then controlling changes and communicating to relevantstakeholders.

A.communicating

B.collecting

C.filing

D.documenting


正确答案:D
需求管理过程是(1),分析,跟踪,优先考虑和同意的要求并控制变化和沟通,利益相关者。A、沟通B、收集C、归档D、编制

第5题:

“Cost of quality”is a project management concept that includes cost of( 73)

A.exceedings requirements

B.Changes to the requirements

C.Ensuring conformance to requirements

D.The quality control requirements


正确答案:C

第6题:

Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.

A.Developing project charter

B.Developing project management plan

C.Analyzing project risks

D.Monitoring and controlling project


正确答案:C

第7题:

● In requirements engineering,requirements elicitation is the practice of collecting the requirements of a system from users,customers and other stakeholder. In the following practices,__(73)__is rarely used in requirements elicitation.

(73)A.brain storming B.interview

C.questionnaire D.Monte Carlo analysis


正确答案:D
在需求工程,需求获取是从用户,客户和其他干系人收集一个系统的需求的做法。下列做法中,蒙特卡罗分析是很少用于需求获取。

第8题:

The(69)Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

A.Plannlng

B.Executing

C.Monitoring and Controlling

D.Closing


正确答案:B
解析:执行过程组由用于完成为达成项目要求而在项目管理计划中定义的工作的过程组成。

第9题:

Requirements management is the process of ( 73 ),analyzing, tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome (product or service) should conform.

A.communicating

B.collecting

C.filing

D.documenting


正确答案:D

第10题:

Is requirements engineering,requirements elietation is the practiceof collecting the requirements of a system frce users,customers and other stakeholders. Is the following practices ()is rarely used in requirements elicltation

A.brain storning

B.interview

C.questionnaire

D.monte carlo analysis


正确答案:D