第1题:
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.
A.analyze
B.track
C.level
D.extend
第2题:
● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
(72)
A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain method
第3题:
A.PERT
B.Resourceleveling
C.Schedulecompression
D.Critical chain method
第4题:
is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships:(67), the initiation of the successor activity, depends upon the completion of the predecessor activity.(68), the initiation of the successor activity, depends upon the initiation of the predecessor activity.
A.PDM
B.CPM
C.PERT
D.AOA
第5题:
● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between
them.
(73)
A.PERT
B.AOA
C.WBS
D.PDM
第6题:
●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.
(75)
A. analyze
B. track
C. level
D. extend
第7题:
______is one of the techniques used for estimating activity durations.
A.Analogous Estimating
B.Precedence Diagramming Method(PDM)
C.Dependency Determination
D.Schedule network Templates
第8题:
● (73) is one of the techniques used for estimating activity durations.
(73)
A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates
第9题:
(b) Describe a framework to assess the risks to the progress of the Giant Dam Project. Your answer should
include a diagram to represent the framework. (6 marks)
(b) Framework for assessing risk
Risk is assessed by considering each identified risk in terms of two variables:
– its hazard (or consequences or impact) and,
– its probability of happening (or being realised or ‘crystallising’).
The most material risks are those identified as having high impact/hazard and the highest probability of happening. Risks
with low hazard and low probability will have low priority whilst between these two extremes are situations where judgement
is required on how to manage the risk.
In practice, it is difficult to measure both variables with any degree of certainty and so if is often sufficient to consider each
in terms of relative crude metrics such as ‘high/medium/low’ or even ‘high/low’. The framework can be represented as a ‘map’
of two intersecting continuums with each variable being plotted along a continuum.
第10题:
is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the logical relationships that exist between them. A.PERT B.AOA C.WBS D.PDM