软件水平考试

( )is a process of developing a detailed description of the project and productA.collect requirements B.Scope definition C.validate scope D.Control range

题目
( )is a process of developing a detailed description of the project and product

A.collect requirements
B.Scope definition
C.validate scope
D.Control range
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

( ) describes, in detail, the project’ s deliverables and the work required to create those deliverables.

A.Product scope description B.Project objectives C.Product specification D.The project scope statement


正确答案:D

第2题:

Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.()process does not belong to Project Integration Management.

A.Developing project charter

B.Developing project management plan

C.Analyzing project risks

D.Monitoring and controlling project


正确答案:C

第3题:

Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.

A.analyze

B.track

C.level

D.extend


正确答案:B
解析:通常,制订项目进度计划是一个反复迭代的过程,该过程确定每个活动和每个里程碑的开工日期和完成日期。制订进度过程要求对历时估算和资源估算进行评审和修订,从而产生一个经过认可的项目进度表,作为对项目进展进行追踪的基准。

第4题:

Requirements management is the process of ( 73 ),analyzing, tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome (product or service) should conform.

A.communicating

B.collecting

C.filing

D.documenting


正确答案:D

第5题:

It can be inferred from the passage that in artistic creation______.

A.product is more important than process

B.process is more important than product

C.process and product are equally important

D.both process and product are unimportant


正确答案:B
解析:推理判断题。由第四段第二、三、四句可知:父母不应该说“我不会画直线”,他们应该说“我喜欢创新”,因为这会告诉孩子创新的过程比产物重要。可推知,在艺术创新中,过程比产物重要。因此,B项符合题意。

第6题:

Project Quality Management must address the management of the project and the ()of the project.While Project Quality Management applies to all projects, regardless of the nature of their product,product quality measures and techniques are specific to the particular type of product produced by the project.()A.performance B.process C.product D.object


正确答案:C

项目质量管理必需专注于对项目和项目产品的管理。当所有的项目在运用项目质量管理时,无论项目产品的本质如何,都要依据项目所产生产品的类型明确产品质量的度量和技术。

第7题:

()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service,or result acceptance by validating each deliverable。

A、Validate scope

B、Define scope

C、Control scope

D、Collect requirement


正确答案:C

第8题:

●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.

(75)

A. analyze

B. track

C. level

D. extend


正确答案:B

第9题:

● Plan Quality is the process of identifying quality requirements and standards for the project and product, and documenting how the project will demonstrate compliance.(75) is a method that analyze all the costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraising the product or service for conformance to requirement, and failing to meet requirements.

(75)

A.Cost-Benefit analysis

B.Control charts

C.Quality function deployment

D.Cost of quality analysis


正确答案:D
试题(75)分析
 质量分析成本Cost of quality analysis是对产品或服务进行需求一致性分析所产生的成本;
 成本效益分析Cost-Benefit analysi是通过比较项目的全部成本和效益来评估项目价值的一种方法;
 控制图Control charts是项目质量控制方法;
 质量功能展开Quality function deployment是把顾客或市场的要求转化为设计要求、零部件特性、工艺要求、生产要求的多层次演绎分析方法
 因此,因此选D
参考答案
(75)D

第10题:

(接上一题)It is a(2)process throughout a project. A requirement is a capability to which aproject outcome(product or service)should conform.

A.persistent

B.continuing

C.permanent

D.continuous


正确答案:D
这是一个(2)在整个项目过程。的要求是一种能力,项目成果(产品或服务)应符合。A、坚持的B、继续的C、永久的D、连续的

更多相关问题