第1题:
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
该题的关键词为"schedule activity durations",其语句结构为"The process(主语)of()schedule activity durations uses(谓语)information",语句的含义为"(?)进度活动持续时间的过程使用信息",结合选项,此处应该选择动词,所以观察对进度活动持续时间采取什么行为会应用到各种信息(information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities),只有在估算进度活动持续时间时才会使用这些信息得到活动的工期,其他选项容易排除,因而选项A符合题意要求。
第2题:
● Scope management is:
A a project control function.
B employs change control.
C a work authorization process.
D considers Cost, Quality and Schedule.
E All of the above.
第3题:
Scope management is:
A.a project control function.
B.employs change control.
C.a work authorization process.
D.considers Cost, Quality and Schedule.
E.All of the above.
第4题:
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第5题:
● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
第6题:
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
第7题:
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.
(74)
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第8题:
A.activity duration estimating, schedule developing, activity resource estimating
B.activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
第9题:
● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.
(71)
A.activity duration estimating, schedule developing, activity resource estimating
B . activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating
第10题:
● Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.
(74)
A.scope statement
B.activity list
C.project charter
D.project schedule