第1题:
167 The project life-cycle can be described as:
A. project concept, project planning, project execution, and project close-out.
B. project planning, work authorization, and project reporting.
C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.
E. All of the above
第2题:
67 Life Cycle Costing:
A. is the concept of including all costs within the total life of a project.
B. is an activity devoted to optimizing cost/performance
C. is an activity of appraising the cost and technical performance of a completed project.
D. is a process of predicting the life of a project.
E. None of the above.
第3题:
The project life-cycle can be described as:
A.project concept, project planning, project execution, and project close-out.
B.project planning, work authorization, and project reporting.
C.project planning, project control, project definition, WBS development, and project termination.
D.project concept, project execution, and project reporting.
E.All of the above.
第4题:
● A project life cycle is a collection of generally sequential project (73)whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74)for managing the project, regardless of the specific work involved.
(73)
A. phases
B. processes
C. segments
D. pieces
(74)
A. plan
B. fraction
C. main
D. framework
第5题:
Define Activities is the process of identifying the specific actions to be performed to produce the (71).
A.project elements
B.work drafts
C.work package
D.project deliverables
第6题:
185 Life Cycle Costing:
A. is the concept of including all costs within the total life of a project.
B. is an activity devoted to optimizing cost/performance
C. is an activity of appraising the cost and technical performance of a completed project.
D. is a process of predicting the life of a project.
E. None of the above
第7题:
● A Work Breakdown Structure:
A assures all work is identified
B subdivides the project into manageable segments
C provides the project sponsor with a time-phase task summary
D both A and B
E All of the above.
第8题:
During which phase of the project life cycle is the amount at stake lowest?
A concept
B development
C execution
D conclusion
E C and D
第9题:
● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).
(71)
A. project elements
B. work drafts
C. work package
D. project deliverables
第10题:
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting