第1题:
171 Documented work authorization provide:
A. a means of effective internal coordination of the project's activities.
B. an audit trail of all work authorized from project initiation to completion
C.a means for communication of work activity between the project manager and the performing activities.
D. All of the above
E. A and B only
第2题:
● Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.
(74)
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第3题:
Documented work authorization provide:
A.a means of effective internal coordination of the project's activities.
B.an audit trail of all work authorized from project initiation to completion.
C.a means for communication of work activity between the project manager and the performing activities.
D.All of the above
E.A and B only.
第4题:
______is the application of planned,systematic quality activities to ensure that the project will employ all processes needed to meet requirements.
A.euality assurance(QA)
B.Quality planning
C.Quality control(QC)
D.Quality costs
第5题:
● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.
t
A.Integration
B.Scope
C.Configuration
D.Requiremen
第6题:
Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.
A.Project
B.project management team
C.performingorganization
D.customer
该题的关键词为"determine quality policies,objectives and responsibilities",其语句结构为"Project Quality Management processes(主语)include(谓语)all the activities of the (宾语)that determine quality policies,objectives and responsibilities(定语从句)",含义为"项目质量管理过程包括决定质量政策、质量目标以及质量责任的什么的所有活动",根据项目质量管理知识,只有组织才可以决定项目的质量政策,因而此处选择选项C。
第7题:
● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.
(73)
A. Quality assurance (QA)
B. Quality planning
C. Quality control (QC)
D. Quality costs
第8题:
● Project Quality Management processes include all the activities of the (71) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
(71)
A. project
B. project management team
C. performing organization
D. customer
第9题:
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
第10题:
The( )Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements. A.Planning B.Executing C.Monitoring and Controlling D.Close-out