第1题:
Going from Level to Level in the work breakdown structure will result in
A.Less estimating accuracy
B.Better control of the project
C.Lower status reporting costs
D.A greater likelihood that something will fall through the cracks
E.None of the above
第2题:
The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A.Work packages.
B.Subtasks.
C.Tasks.
D.Code of accounts.
E.Integration points.
第3题:
The work breakdown structure (WBS) is first developed in which scope management process?
A . Initiation
B . Scope planning
C . Scope change control
D . Scope Definition
E . Scope verification
第4题:
45 A clear definition of the user's needs serves as the direct basis for the:
A. Work breakdown structure.
B. Functional requirements.
C. Project cost estimate.
D. Selection of personnel.
E. Termination decision.
第5题:
87 Which of the following would most likely increase the accuracy of estimating the project cost? A. Pricing out the work at lower levels in the work breakdown structure.
B. Using historical data.
C. Talking to people who have worked on similar projects.
D. All of the above.
E. A and C only.
第6题:
A clear definition of the user's needs serves as the direct basis for the:
A.Work breakdown structure.
B.Functional requirements.
C.Project cost estimate.
D.Selection of personnel.
E.Termination decision.
第7题:
Which of the following would most likely increase the accuracy of estimating the project cost?
A . Pricing out the work at lower levels in the work breakdown structure.
B . Using historical data.
C . Talking to people who have worked on similar projects.
D . All of the above.
E . A and C only.
第8题:
When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A.task
B.level of effort
C.sub-task
D.project
E.work package
第9题:
106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A. Work packages.
B. Subtasks.
C. Tasks.
D. Code of accounts.
E. Integration points
第10题:
51 Going from Level 2 to Level 4 in the work breakdown structure will result in
A. Less estimating accuracy
B. Better control of the project
C. Lower status reporting costs
D. A greater likelihood that something will fall through the cracks
E. None of the above