A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the proj

题目

A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved. 空白(1)处应选择()

  • A、phases
  • B、processes
  • C、segments
  • D、pieces
参考答案和解析
正确答案:A
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

QUEST . Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

A . 5%

B . 10%

C . 15%

D . 25%

E . 50%


正确答案:D

第2题:

67 The project stakeholders should be actively involved with the _____ phase(s) of the life cycle. A. Conceptual

B. Development.

C. Execution

D. Finish

E. All of the above


正确答案:E

第3题:

The project life-cycle can be described as:

A.project concept, project planning, project execution, and project close-out.

B.project planning, work authorization, and project reporting.

C.project planning, project control, project definition, WBS development, and project termination.

D.project concept, project execution, and project reporting.

E.All of the above.


正确答案:A
A

第4题:

● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

A 5%

B 10%

C 15%

D 25%

E 50%


正确答案:D

第5题:

185 Life Cycle Costing:

A. is the concept of including all costs within the total life of a project.

B. is an activity devoted to optimizing cost/performance

C. is an activity of appraising the cost and technical performance of a completed project.

D. is a process of predicting the life of a project.

E. None of the above


正确答案:A

第6题:

During which phase of the project life cycle is the amount at stake lowest?

A concept

B development

C execution

D conclusion

E C and D


正确答案:A

第7题:

167 The project life-cycle can be described as:

A. project concept, project planning, project execution, and project close-out.

B. project planning, work authorization, and project reporting.

C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.

E. All of the above


正确答案:A

第8题:

The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.

A.Conceptual

B.Development.

C.Execution

D.Finish

E.All of the above.


正确答案:E
E

第9题:

67 Life Cycle Costing:

A. is the concept of including all costs within the total life of a project.

B. is an activity devoted to optimizing cost/performance

C. is an activity of appraising the cost and technical performance of a completed project.

D. is a process of predicting the life of a project.

E. None of the above.


正确答案:A

第10题:

● The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.

A Conceptual

B Development.

C Execution

D Finish

E All of the above.


正确答案:E