CMS专题

单选题A Customer has a proprietary server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible for deployment with their provis

题目
单选题
A Customer has a proprietary server deployment solution that uses a combination of disk imaging and application pushing technology. They need to get a working Windows 2003 image for their new servers as soon as possible for deployment with their provisioning system. Which of the following methods can achieve this?()
A

UseServerGuide to install Windows 2003rchase PowerVM Standard Edition for the entire system

B

Install Windows 2003 using the F6 supply Mass Storage Controller option

C

Replace Customer’s deployment solution with Tivoli Provisioning Manager for OS Deployment Director Edition

D

Deploy Customer’s existing image and useUXSPi to update IBM specific drivers

如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A customer wants to deploy the Cisco Business Ready Teleworker solution, but is currently using a traditional (non-IP) PBX for voice services. What would you recommend to this customer?()

  • A、Deployment of Business Ready Teleworker with VoIP is not recommended.
  • B、The customer’s existing PBX must first be replaced with Cisco IP Telephony solution.
  • C、Business Ready Teleworker and Cisco IP Telephony can be deployed in parallel to the existing PBX, integrating the two with trunking.
  • D、Deployment is recommended only for full-time Teleworkers who have no other corporate phone.

正确答案:C

第2题:

A major account is considering migrating from a proprietary Unix server to a Linux and Intel-based platform. They are not sure if the Intel-based server will be able to handle the workload of the Unix server.  What would be the best strategy to win with an IBM solution?()

  • A、Suggest to the customer to send their administrator to IBM System x training class to learn more about IBM Intel based servers.
  • B、Propose a try and buy option and offer to help the customer in sizing the new Linux server. Engage the system Engineer on this opportunity.
  • C、Introduce the IBM pSeries Unix product specialist to the account because IBM operating system (AIX) offers an open Unix solution.
  • D、Direct the customer to the IBM Web site to help with sizing and System x server models and types. Follow-up with the customer to answer any sizing question.

正确答案:B

第3题:

A customer has a very large number of physical Windows-based servers and no centralized storage. Which technology solution will help the customer to reduce the footprint of their existing server estate?()

A. z/OS, DS8000, TSM

B. TSM, LTO-5, VMware

C. System x, VMware, XIV

D. System p, VMware, DS5000


参考答案:C

第4题:

A solution provider has proposed a pSeries solution to a new customer.  The solution is complex with a number of technologies that are new to the customer. They have a tight timeline for implementation.  The solution provider has not been able to get a clear understanding as to how the customer will backup the system.  What would be the most appropriate action to address the risks with this solution?()

  • A、Sell Sysback
  • B、Conduct a SAR
  • C、Sell Supportline
  • D、Provide a project timeline

正确答案:B

第5题:

A customer has a very large number of physical Windows-based servers and no centralized storage. Which technology solution will help the customer to reduce the footprint of their existing server estate?()

  • A、z/OS, DS8000, TSM
  • B、TSM, LTO-5, VMware
  • C、System x, VMware, XIV
  • D、System p, VMware, DS5000

正确答案:C

第6题:

During consultation, you find that a customer has only a single asset closet and is looking for a solution that is easy to deploy. Which NAS physical deployment model would you suggest to this customer?()

  • A、edge
  • B、central
  • C、Layer2
  • D、Layer3

正确答案:A

第7题:

A customer has just purchased six x346 servers running Windows 2003 Web Edition.They are expecting to add six additional x346’s in three months.They have a requirement to automatically deploy the current server image upon the new servers. What TWO actions are required to complete this task?()

  • A、Ensure Director Agent is installed on the new servers.
  • B、Ensure a DHCP Sever is installed and configured in the environment.
  • C、Ensure Server Plus Pack option has been installed and configured.
  • D、Ensure Software Distribution has been installed on the IBM Director Server and an image has been created.
  • E、Ensure Remote Deployment Manager has been installed on the IBM Director Server and an image has been created.

正确答案:B,E

第8题:

An SMB customer requires a tower server with 2TB of internal storage. The customer has requested a low cost solution.  What IBM System x server would satisfy this criteria?()

  • A、x3250
  • B、x3200
  • C、x3650
  • D、x3400

正确答案:B

第9题:

A customer is interested in a power efficient server solution. The Sales Specialist has recommended a BladeCenter solution. The customer debates the price is high compared to rack servers.  Which of the following should the Sales Specialist emphasize to address the pricing difference?()

  • A、Higher rack density that reduces data center footprints
  • B、Internal upgrades that only IBM can offer
  • C、Total Cost of Ownership (TCO) related to innovative components such as Integrated Switches 
  • D、The Rear Door Heat eXchanger that only IBM can offer

正确答案:C

第10题:

A customer has been working with your company to purchase an iDataPlex cluster. They have a configuration from IBM and are getting ready to place an order. Which should be done of the following?()

  • A、A solution sizing questionnaire
  • B、Verify the customer has the proper racks
  • C、A Technical Delivery Assessment
  • D、Verify the customer has enough cooling in the computer room

正确答案:C