单选题Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()A independentresourceB individualworkloadC workmilestoneD workpackage

题目
单选题
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
A

independentresource

B

individualworkload

C

workmilestone

D

workpackage

如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

A negative cost variance and positive schedule variance means:

A The project is under budget and ahead of schedule

B The project is over budget and behind schedule

C The project is over budget and ahead of schedule

D The project will be overrun but ahead of schedule at completion


正确答案:C

第2题:

171 Documented work authorization provide:

A. a means of effective internal coordination of the project's activities.

B. an audit trail of all work authorized from project initiation to completion

C.a means for communication of work activity between the project manager and the performing activities.

D. All of the above

E. A and B only


正确答案:D

第3题:

Documented work authorization provide:

A.a means of effective internal coordination of the project's activities.

B.an audit trail of all work authorized from project initiation to completion.

C.a means for communication of work activity between the project manager and the performing activities.

D.All of the above

E.A and B only.


正确答案:D
D

第4题:

● The project life-cycle can be described as(72).

(72)

A.project concept, project planning, project execution, and project close-out

B.project planning, work authorization, and project reporting

C.project planning, project control, project definition, WBS development, and project termination

D.project concept, project execution, and project reporting


正确答案:A

试题(72)分析
  关于项目周期划分正确的是  (72)  。
  A.启动、计划、执行、收尾
  B.计划、授权、报告
  C.计划、控制、方案设计、WBS的发展、终止
  D.启动、执行、报告
参考答案
  (72)A

第5题:

● The Work Breakdown Structure (WBS) is the basis for communicating:

A Project scope, cost control, schedule, quality

B Project objectives, dependencies, plan, cost control

C Project scope, schedule, staffing, cost control

D Project scope, quality, schedule, dependencies

E Project budget, schedule, risk factors, work assignments.


正确答案:A

第6题:

167 The project life-cycle can be described as:

A. project concept, project planning, project execution, and project close-out.

B. project planning, work authorization, and project reporting.

C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.

E. All of the above


正确答案:A

第7题:

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

A.independentresource

B.individualworkload

C.workmilestone

D.workpackage


参考答案:D

第8题:

The project life-cycle can be described as:

A.project concept, project planning, project execution, and project close-out.

B.project planning, work authorization, and project reporting.

C.project planning, project control, project definition, WBS development, and project termination.

D.project concept, project execution, and project reporting.

E.All of the above.


正确答案:A
A

第9题:

● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.

(75)

A.independent resource

B.individual work load

C.work milestone

D.work package


正确答案:D
试题(75)分析
 WBS工作分解结构是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包work package的层次。
 独立资源independent resource、个人工作负荷individual work load以及工作里程碑work milestone都不是WBS分解的最小层级,因此选D。
参考答案
(75)D

第10题:

means that every project has a definite beginning and a definite end.

A.Project phase

B.Unique

C.Temporary

D.Closure


正确答案:C
解析:临时性是指每一个项目都有一个明确的开始时间和结束时间。