第1题:
A negative cost variance and positive schedule variance means:
A The project is under budget and ahead of schedule
B The project is over budget and behind schedule
C The project is over budget and ahead of schedule
D The project will be overrun but ahead of schedule at completion
第2题:
171 Documented work authorization provide:
A. a means of effective internal coordination of the project's activities.
B. an audit trail of all work authorized from project initiation to completion
C.a means for communication of work activity between the project manager and the performing activities.
D. All of the above
E. A and B only
第3题:
Documented work authorization provide:
A.a means of effective internal coordination of the project's activities.
B.an audit trail of all work authorized from project initiation to completion.
C.a means for communication of work activity between the project manager and the performing activities.
D.All of the above
E.A and B only.
第4题:
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
第5题:
● The Work Breakdown Structure (WBS) is the basis for communicating:
A Project scope, cost control, schedule, quality
B Project objectives, dependencies, plan, cost control
C Project scope, schedule, staffing, cost control
D Project scope, quality, schedule, dependencies
E Project budget, schedule, risk factors, work assignments.
第6题:
167 The project life-cycle can be described as:
A. project concept, project planning, project execution, and project close-out.
B. project planning, work authorization, and project reporting.
C. project planning, project control, project definition, WBS development, and project termination. D. project concept, project execution, and project reporting.
E. All of the above
第7题:
A.independentresource
B.individualworkload
C.workmilestone
D.workpackage
第8题:
The project life-cycle can be described as:
A.project concept, project planning, project execution, and project close-out.
B.project planning, work authorization, and project reporting.
C.project planning, project control, project definition, WBS development, and project termination.
D.project concept, project execution, and project reporting.
E.All of the above.
第9题:
● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
(75)
A.independent resource
B.individual work load
C.work milestone
D.work package
第10题:
means that every project has a definite beginning and a definite end.
A.Project phase
B.Unique
C.Temporary
D.Closure