Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.A.independent resource B.individual work load C.work milestone D.work package

题目
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the ( ) level.

A.independent resource
B.individual work load
C.work milestone
D.work package
如果没有搜索结果,请直接 联系老师 获取答案。
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

The()describes, in detail, the project's deliverables and the work required to create those deliverables.

A.project scope statement

B.project requirement

C.project charter

D.product specification


参考答案:A

第2题:

● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.

(75)

A.independent resource

B.individual work load

C.work milestone

D.work package


正确答案:D
试题(75)分析
 WBS工作分解结构是面向可交付物的层次性分析结构,是对完成项目目标、创造可交付物所需执行的项目工作的分解。WBS把项目工作细分为更小、更易管理的工作单元,随着WBS层次的降低,意味着项目工作也越来越详细,直到工作包work package的层次。
 独立资源independent resource、个人工作负荷individual work load以及工作里程碑work milestone都不是WBS分解的最小层级,因此选D。
参考答案
(75)D

第3题:

● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

(73)

A. work performance information

B. scope statement

C. change requests

D. process analysis


正确答案:B

第4题:

● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)

(74)

A. Scope Planning

B. Scope Verification

C. Scope Change Control

D. Scope Definition


正确答案:D

第5题:

______describes,in detail,the project's deliverables and the work required to create those deliverables.

A.Product scope description

B.Project objectives

C.Stakeholder Analysis

D.The project scope statement


正确答案:D
解析:项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。
选项A是产品范围说明书,选项B是项目目标,选项C是干系人分析,选项D是项目范围说明书。故D是正确的。

第6题:

●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.

(74) A. Product scope description

B. Project objectives

C. Product specification

D. The project scope statement


正确答案:D

第7题:

The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteria

A.work performance information

B.scope statement

C.change requests

D.process analysis


正确答案:B

第8题:

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

A.independentresource

B.individualworkload

C.workmilestone

D.workpackage


参考答案:D

第9题:

The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.

A.work performance information

B.scope statement

C.change requests

D.process analysis


正确答案:B
解析:项目范围说明书是制订质量计划的—项关键输入,这是因为它记载了项目的主要可交付成果以及用于确定重要项目干系人需求的项目目标、限值和验收标准。

第10题:

()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.

A.The project charter

B.The project scope statement

C.The WBS dictionary

D.The activity list


正确答案:C

更多相关问题