单选题An administrator has had a request from the data center for method to monitor the status of an  HACMP cluster. The monitoring software environment currently used is not compatible with SNM at this time, and there is not time to crate a new tool. There 

题目
单选题
An administrator has had a request from the data center for method to monitor the status of an  HACMP cluster. The monitoring software environment currently used is not compatible with SNM at this time, and there is not time to crate a new tool. There is also a restriction that the data center personnel not be allowed to login to the HACMP cluster nodes. What method will provide the solution for customer?()
A

 The clstat.cgi program will provide a solution.

B

 The customer must install Tivoli with the HACMP plugin for monitoring the cluster.

C

 The clinfo program included in the HACMP distribution will solve the monitoring issues.

D

 Customize the cluster to send error notifications for every event to an email at the network control center.

参考答案和解析
正确答案: B
解析: 暂无解析
如果没有搜索结果,请直接 联系老师 获取答案。
相似问题和答案

第1题:

Refer to the exhibit. ROUTE.com has just implemented this EIGRP network. A network administrator came to you for advice while trying to implement load balancing across part of their EIGRP network. If the variance value is configured as 2 on all routers and all o ther metric and K values are configured to their default values, traffic from the Internet to the data center will be load balanced across how many paths? ()

A. 1

B. 2

C. 3

D. 4

E. 5


参考答案:C

第2题:

Which two design recommendations are most appropriate when EIGRP is the data center corerouting protocol? ()

  • A、 Summarize data center subnets.
  • B、 Use passive interfaces to ensure appropriate adjacencies.
  • C、 Tune the EIGRP timers to enable EIGRP to achieve quicker convergence.
  • D、 Adjust the default bandwidth value to ensure proper bandwidth on all links.
  • E、 Advertise a default summary route into the data center core from the aggregation layer.

正确答案:A,E

第3题:

When data() , it has to be analyzed to decide what it all means.

A.had been collected

B.has collected

C.has been collected


参考答案:C

第4题:

A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored?()

  • A、Identify which systems are the most critical and bring them up by level of importance.
  • B、Retrieve the latest backup tapes for immediate system restore using the GFS rotation.
  • C、Identify the least critical systems and then power those systems on first.
  • D、Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.

正确答案:A

第5题:

An administrator is creating a redundant environment for a current data center. A backup site must be available if the entire data center site should become unavailable. To reduce costs, this backup site does not need to be up and running at all times ready for failover. It must contain equipment and the ability to restore data from the data center.  Which of the following site types should be considered to meet these requirements? ()

  • A、 Hot site
  • B、 Warm site
  • C、 Cold site
  • D、 Active failover site

正确答案:B

第6题:

Which two design recommendations are most appropriate when EIGRP is the data center core routing protocol?()

A. Summarize data center subnets.

B. Use passive interfaces to ensure appropriate adjacencies.

C. Tune the EIGRP timers to enable EIGRP to achieve quicker convergence.

D. Adjust the default bandwidth value to ensure proper bandwidth on all links.

E. Advertise a default summary route into the data center core from the aggregation layer.


参考答案:A, E

第7题:

An administrator is planning an upgrade of a major software package on an application server.The software has been identified, the project approved and the upgrade purchased. Which of the following steps should the administrator take NEXT?()

  • A、Create a test environment for the new version.
  • B、Determine system requirements for the upgrade.
  • C、Request bids from other competing vendors in the product space.
  • D、Document the upgrade.

正确答案:A

第8题:

An administrator is creating a redundant environment for a current data center. A backup site must be available if the entire data center site should become unavailable. To reduce costs, this backup site does not need to be up and running at all times ready for failover. It must contain equipment and the ability to restore data from the data center.Which of the following site types should be considered to meet these requirements?()

A. Hot site

B. Warm site

C. Cold site

D. Active failover site


参考答案:B

第9题:

An administrator has experienced minor electrical shocks when touching metal surfaces in the data center. Which of the following is the MOST likely cause?()

  • A、The UPS is using 220-240V rather than 110-120V
  • B、The humidity is too low
  • C、The temperature is too low
  • D、The datacenter is experiencing EMI

正确答案:B

第10题:

An SNMP alert has been generated by a server in the main data center.The alert stated that the internal temperature of the server has exceeded the threshold.No other servers in the rack have experienced problems,and no other alerts have come from that server about any other events.Which of the following is the cause of this issue?()

  • A、Rack cooling equipment failure
  • B、Dust collection in the server
  • C、Server processor failure
  • D、Server power supply failure

正确答案:B